Scrum SPS Scaled Professional Scrum (SPS) Exam Exam Practice Test

Page: 1 / 4
Total 40 questions

Scaled Professional Scrum (SPS) Exam Questions and Answers

Question 1

Scenario A: Nexus Sprint Review with Five Scrum Teams

There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams

present the results of the Sprint. After introductions, each team takes time to present their work

for inspection by individually showing the new features they have built. They are not using a

shared environment. The stakeholders do not provide much feedback. The event ends and

people filter out of the room.

Since teams are not using a shared environment, what is likely?

(choose the best two answers)

Options:

A.

The Sprint is too short.

B.

The Nexus has not yet reached the integration phase.

C.

There is no single Integrated Increment.

D.

The Nexus Integration Team is lacking or nonexistent.

Question 2

If two Scrum Teams are added to a product that previously had only one Scrum Team, what will

be the immediate impact on the productivity of the original Scrum Team?

(choose the best answer)

Options:

A.

Its productivity is likely to stay the same.

B.

Its productivity is likely to decrease.

C.

Its productivity is likely to increase.

Question 3

True or False: When multiple Scrum Teams are working together on the same product, each

team should maintain a separate Product Backlog.

Options:

A.

True

B.

False

Question 4

True or False: A Nexus Integration Team is responsible for actually doing the integration work

during the Sprint.

Options:

A.

True

B.

False

Question 5

Scenario A: Nexus Sprint Review with Five Scrum Teams

There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams

present the results of the Sprint. After introductions, each team takes time to present their work

for inspection by individually showing the new features they have built. They are not using a

shared environment. The stakeholders do not provide much feedback. The event ends and

people filter out of the room.

If this pattern of Nexus Sprint Reviews continues for multiple Sprints, what may be the effects?

(choose the best two answers)

Options:

A.

There will be more and more work to inspect so teams will need their own

individual Sprint Reviews.

B.

Quality will degrade as the teams delay creating a single Integrated Increment.

C.

Empiricism will suffer as the teams cannot produce a shared velocity.

D.

Ability to adapt will suffer as the stakeholders continue to disengage and not

give feedback.

Question 6

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What would you recommend to the two teams that are continually dependent on each other to

help them manage their work?

(choose the best answer)

Options:

A.

The Nexus Integration Team should be responsible for integrating the work of these

two Scrum Teams.

B.

Reorganize these two Scrum Teams so that one is responsible for development and

one is responsible for integration.

C.

Merge the two Scrum Teams together.

D.

Ensure the appropriate representatives from both teams are present during Cross-

Team Refinement.

Question 7

True or False: There is one Product Backlog for a Nexus.

Options:

A.

True

B.

False

Question 8

What is the purpose of the Nexus Sprint Retrospective?

(choose the best answer)

Options:

A.

To review the feedback from the Sprint Review and decide what actions to take.

B.

To ensure all Scrum Teams are working on the same improvement actions.

C.

To identify underperforming team members and recommend corrective action.

D.

None of the above.

Question 9

From the list below, what is the most important concern for multiple Scrum Teams when they

are working from the same Product Backlog?

(choose the best answer)

Options:

A.

Meeting original scope projections.

B.

Minimizing dependencies between teams.

C.

Clear definition of requirements.

D.

Making sure there is enough work for everyone on every team.

Question 10

The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver

a valuable and useful Increment. What could they try to improve their ability to produce an

Increment for the next Sprint?

(choose the best answer)

Options:

A.

Reduce the amount of work that the teams pull into the Sprint.

B.

Ask the Nexus Integration Team to extend the Sprint to allow more time for

integration.

C.

Reduce the number of Scrum Teams to reduce complexity.

D.

Add another Scrum Team to the Nexus to increase capacity.

Question 11

Who has overall responsibility for ensuring Nexus Sprint Retrospective occurs?

(choose the best answer)

Options:

A.

The Scrum Master on the Nexus Integration Team.

B.

Any Scrum Master from the Nexus.

C.

The Nexus Integration Team.

D.

The Developers.

Question 12

The purpose of the Nexus Sprint Backlog is:

(choose the best two answers)

Options:

A.

To make the work of the Nexus Integration Team transparent.

B.

To provide a view of dependent Product Backlog items in a Sprint.

C.

To visualize all Product Backlog items.

D.

To make dependencies transparent to the Scrum Teams.