New Year Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Exam Practice Test

Page: 1 / 8
Total 80 questions

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

First in first out (FIFO)

B.

Simultaneous

C.

Manual maintenance

D.

100% check

Question 2

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.

Options:

A.

Planned delivery time

B.

Total replenishment lead time

C.

Operation duration

D.

Inhouse production time

Question 3

Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

Options:

A.

Use batch determination.

B.

Use the Batch Information Cockpit.

C.

Use the batch whereused list.

D.

Use batch derivation.

Question 4

Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.

Options:

A.

Schedule production orders.

B.

Check material availability.

C.

Select master data.

D.

Define integration with cost accounting.

Question 5

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?

Note: There are 2 correct answers to this question.

Options:

A.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

B.

Add the agreement to the source list mark it for MRP relevance.

C.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

D.

Add the agreement to the quota arrangement mark it for MRP relevance.

Question 6

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

Options:

A.

Execute an infinite production planning run for the critical resources.

B.

Reduce the planning time interval.

C.

Determine a time period with available capacity on the planning board.

D.

Increase the capacity supply in a timephased interval.

E.

Form optimum sequences to reduce setup times.

Question 7

Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Assign planned orders manually in the planning table.

B.

Run MRP with quota arrangement.

C.

Run MRP with automatic selection of production version.

D.

Run PP/DS heuristics for repetitive manufacturing.

Question 8

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.

Options:

A.

Queue time

B.

Teardown time

C.

Move time

D.

Setup time

Question 9

You are a consultant on an SAP S/4HANA Cloud Greenfield project.

Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.

Options:

A.

Efficiency

B.

Accuracy

C.

Timeliness

D.

Stability

Question 10

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with an alternative sequence in the routing

C.

A production line with a parallel sequence in the routing

D.

A production line with prioritized alternative work centers

Question 11

You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

Options:

A.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.

B.

Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.

D.

Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.

Question 12

What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?

Options:

A.

The MRP run assumes external procurement.

B.

The MRP run assumes inhouse production.

C.

The MRP run plans the material only if a quotation has been maintained.

D.

The MRP run does NOT consider the material; it has to be planned interactively.

Question 13

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Planned order

B.

Scheduling agreement schedule line

C.

Production order

D.

Purchase order

Question 14

You want to reduce planning efforts for B C classified materials. Which planning procedure do you recommend?

Options:

A.

Consumption Based Planning

B.

Subassembly Planning

C.

Advanced Planning

D.

Material Requirements Planning

Question 15

How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By order confirmation

C.

By order release

D.

By mass processing

Question 16

What are some SAP recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.

Options:

A.

Establish an organizational structure technical foundation transformation methodology for clean core.

B.

Integrate clean core practices in the endtoend value process chain.

C.

Establish release management.

D.

Establish regular housekeeping tasks procedures.

E.

Define roles responsibilities as part of a process transformation office.

Question 17

For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.

Options:

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing.

B.

The consistency check must be performed.

C.

The assigned routing bill of material (BOM) must be valid in the entire validity period.

D.

The assigned routing bill of material (BOM) must have the same validity period.

E.

The lot size range must be within the lot size range of the assigned routing.

Question 18

Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Variablesize item

B.

Work item

C.

Preliminary item

D.

WBS item

Question 19

During production order creation several valid production versions are found. How does the system choose the production version?

Options:

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Question 20

What are the key features of using a low level code? Note: There are 2 correct answers to this question.

Options:

A.

To determine the priority of alternative components inside ATP

B.

To determine how costs are rolled up by product costing

C.

To determine the sequence in which materials are planned in MRP

D.

To determine the use of subitems inside material BOM (bill of material)

Question 21

What is a work center hierarchy?

Options:

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel

Question 22

Why do you use Engineering Change Management? Note: There are 2 correct answers to this question.

Options:

A.

To monitor document table changes

B.

To enable integration into a sales order

C.

To save multiple changes for an object

D.

To monitor document object changes

Question 23

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

Options:

A.

Post the goods receipt for the finished product.

B.

Reduce run schedule quantities.

C.

Post production costs to the planned order.

D.

Update statistics for the Business Information Warehouse.

E.

Create associated capacity requirements.

Question 24

How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.

Options:

A.

They are created together with the independent requirement for the finished product.

B.

They are created on assembly level during the planning run.

C.

They are created with exact times in Advanced Planning.

D.

They are only created for multilevel bill of material (BOM) structures.

Page: 1 / 8
Total 80 questions