Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.
Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?
Note: There are 2 correct answers to this question.
Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?
Note: There are 2 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
What does a line hierarchy in repetitive manufacturing represent?
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
You want to reduce planning efforts for B C classified materials. Which planning procedure do you recommend?
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.
What are some SAP recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.
For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
During production order creation several valid production versions are found. How does the system choose the production version?
What are the key features of using a low level code? Note: There are 2 correct answers to this question.
What is a work center hierarchy?
Why do you use Engineering Change Management? Note: There are 2 correct answers to this question.
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.