11.11 Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP C_TS422_2022 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Page: 1 / 8
Total 80 questions

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

Run MRP with quota arrangement

B.

Run PP/DS heuristic for repetitive manufacturing

C.

Assign planned orders manually in the planning table

D.

Assign planned orders manually in the planning table

Question 2

What is the work center hierarchy in capacity planning?

Options:

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Question 3

How would you define pegging in the context of Advanced Planning?

Options:

A.

An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements

B.

An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

C.

An evaluation to verify if there are material or capacity shortages in the ^ network after the production planning run

D.

An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

Question 4

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Options:

A.

To increase the number of planning levels

B.

To simplify the structure of bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To reduce the number of changes required in bills of material

Question 5

Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.

what is the impact of this decision?

Note: there are 2 correct answers to this question

Options:

A.

Storage Location MRP areas are required for sales-orders-specific stock.

B.

Net requirement calculation is carried out for every sales order individually.

C.

Both the reduction of make-to-order stock and requirements occur on delivery

D.

Sales orders have to be ATP-confirmed (available-to-promise) to saved.

E.

Production orders are created with sales order reference.

Question 6

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

Options:

A.

Use the Batch Information Cockpit.

B.

Use batch derivation.

C.

Use batch determination

D.

Use the batch where-used list.

Question 7

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

Options:

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

Question 8

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Options:

A.

Create an object selection variant for priority-category-related alerts.

B.

Assign the alert profile to the overall profile.

C.

Create an object selection variant for production-planning-related alerts.

D.

Assign the overall profile to the authorization profile.

Question 9

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Question 10

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Question 11

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

Options:

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Question 12

In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

B.

MRP assigns the capacity requirements automatically after the last scheduled order on a work center.

C.

MRP creates the capacity requirements without checking the work center capacities.

D.

MRP creates the capacity requirements only if the work center has sufficient capacity.

Question 13

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

Options:

A.

Increase the capacity supply in a time-phased interval.

B.

Determine a time period with available capacity on the planning board.

C.

Execute an infinite production planning run for the critical resources.

D.

Reduce the planning Window.

E.

Form optimum sequence to reduce setup times.

Question 14

Which of the following elements does MRP take into account during net requirement

calculation? Note:

There are 2 correct answers to this question.

Options:

A.

Forecast key figures

B.

Safety Stock

C.

Maximum stock level

D.

Purchase orders

Question 15

How can you set up a material as a phantom assembly?

Note: There are 2 correct answers to this question

Options:

A.

Define the special procurement type inside the material master.

B.

Change the item category of the phantom assembly in the bill of material •—' (BOM)

C.

Define the special procurement type inside the BOM

D.

Change the phantom item indicator for the phantom assembly in the bill of material (BOM)

Question 16

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

Options:

A.

Work Center

B.

Production Version

C.

Material

D.

plant

Question 17

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

Options:

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Question 18

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

Options:

A.

Queue

B.

Teardown time

C.

Move time

D.

Setup Time

Question 19

What will happen in the MRP run if you have created a new MRP-relevant material that

supports both in-house production and external procurement?

Options:

A.

The MRP run assumes external procurement.

B.

The MRP run assumes in-house production.

C.

The MRP run does NOT consider the material; it has to be planned interactivelty

D.

The MRP run plans the material only if a quotation has been maintained.

Question 20

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Question 21

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Move Time

B.

Pick/pack time

C.

Setup time

D.

Float before production

E.

Queue time

Question 22

Generic Parent » Generic 1 pt

What is the purpose of collective orders?

Options:

A.

To manage production orders for an entire finished product on multiple levels

B.

To combine order management of co-products and by-products with the main product

C.

To post production costs on a cost collector instead of the production order

D.

To post any component withdrawal as single backflush with order confirmation

Question 23

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.

Note: there are 2 correct answers to this question.

Options:

A.

Manual maintenance

B.

100% check

C.

First in First out (FIFO).

D.

Simultaneous

Question 24

Where do you maintain the work center that represents the production line for repetitive manufacturing?

Note: There are 2 correct answers to this question

Options:

A.

Production cost collector

B.

Repetitive manufacturing profile

C.

Routing

D.

Production version

Page: 1 / 8
Total 80 questions