Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?
Note: There are 2 Correct answers to this question?
Run MRP with quota arrangement
Run PP/DS heuristic for repetitive manufacturing
Assign planned orders manually in the planning table
Assign planned orders manually in the planning table
You cannot plan both quantities and capacities during line loading in repetitive manufacturing by using the following options:
References: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], pages 105-106; [SAP Help Portal: Line Loading in Repetitive Manufacturing].
What is the work center hierarchy in capacity planning?
A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel
A group of alternative work centers providing a cumulative available capacity for production
A group of work centers in a production line being used in sequence for production
A group of alternative work centers for production, structured in hierarchy levels by priorities
A work center hierarchy is a business object in PP/DS that defines the structure and sequence of resources that are used for a production process. You use this object to represent the logical and physical dependencies of the resources and to control the scheduling and sequencing of the operations or orders. A work center hierarchy allows you to modelthe production flow and capacity more realistically and ensure the technical feasibility of the production plan1
A work center hierarchy can also be used to cumulate the available capacity and capacity requirements of the resources in capacity planning. You can cumulate the available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center. This way, you can use a work center hierarchy as a group of alternative work centers that provide a cumulative available capacity for production23
References:
How would you define pegging in the context of Advanced Planning?
An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements
An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements
An evaluation to verify if there are material or capacity shortages in the ^ network after the production planning run
An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run
Pegging is a term used in Advanced Planning to describe the relationship between the receipt and the issue elements of a product within a location. Receipt elements are planning elements that increase the stock of a product, such as production orders, purchase orders, or stock transfers. Issue elements are planning elements that reduce thestock of a product, such as sales orders, planned independent requirements, or reservations. Pegging links the receipt and issue elements according to the bill-of-material structure of all related products and represents the material flow through all levels of production. Pegging enables the system to identify and display quantity and date/time problems, such as shortages or delays, and to forward scheduling changes to other dependent elements. Pegging also forms the basis for the availability check and the capacity check in Advanced Planning12.
References:
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
To increase the number of planning levels
To simplify the structure of bills of material
To reduce the number of material masters
To make the assignment of components easier
To reduce the number of changes required in bills of material
Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly. You can use phantom assemblies for the following purposes:
Phantom assemblies do not increase the number of planning levels, as they are not considered as separate planning objects. They also do not make the assignment of components easier, as the components are assigned to the superordinate product, not to the phantom assembly. References: Phantom Assembly | SAP Help Portal, Phantom Assembly | SAP Help Portal, Planning Phantom Assemblies | SAP Help Portal.
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
Storage Location MRP areas are required for sales-orders-specific stock.
Net requirement calculation is carried out for every sales order individually.
Both the reduction of make-to-order stock and requirements occur on delivery
Sales orders have to be ATP-confirmed (available-to-promise) to saved.
Production orders are created with sales order reference.
In make-to-order production, the production planning is initiated only when a sales order is received. The system does not perform a net requirements calculation between individual sales orders or with the make-to-stock warehouse stock1. Therefore, option B is correct. Additionally, production orders are created with sales order reference, which means that the costs and revenues of the sales order are settled at the end of the production process2. Therefore, option E is also correct. The other options are not valid for make-to-order production. Storage location MRP areas are not required for sales-order-specific stock, as the stock is managed at the sales order level3. The reduction of make-to-order stock and requirements does not occur on delivery, but on goods issue to the sales order1. Sales orders do not have to be ATP-confirmed to be saved, as the availability check is optional and can be performed later. References: 1: Strategies for Make-to-Order (MTO) Production | SAP Help Portal(https://help.sap.com/docs/SAP_S4HANA_CLOUD/2bba750d1e124e1ea2a039bb1cd9b6c5/3b24bf53d25ab64ce10000000a174cb4.html) 2: Outlining Make-to-Order Production - SAP Learning(https://learning.sap.com/learning-journeys/discovering-the-basics-of-sap-s-4hana-manufacturing/outlining-make-to-order-production_be788c36-6fd4-4f1e-b054-635435247918) 3: Storage Location MRP Areas | SAP Help Portal. : Availability Check and Requirements in Sales and Distribution Processing | SAP Help Portal.
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
Note: There are 2 correct answers to this question.
Use the Batch Information Cockpit.
Use batch derivation.
Use batch determination
Use the batch where-used list.
To identify all affected finished goods stocks that contain a deviated raw material batch, you can use the following tools:
Batch derivation and batch determination are not tools to identify affected finished goods stocks, but rather tools to assign batches to production orders or sales orders based on certain criteria. Batch derivation is a process of transferring characteristics or values from one batch to another, while batch determination is a process of finding suitable batches for a requirement based on predefined conditions. References: Batch Information Cockpit | SAP Help Portal, Batch Where-Used List | SAP Help Portal.
Which time elements can be reduced by a reduction strategy?
Note: There are 3 correct answers to this question.
Goods receipt processing time
Move time
Wait time
Float after production
Queue time
A reduction strategy is a method of shortening the lead time of an order by reducingcertain time elements in the order scheduling1. The time elements that can be reduced by a reduction strategy are move time, wait time, and queue time2. Move time is the time required to move a material from one operation to another. Wait time is the time between the end of an operation and the start of the next operation. Queue time is the time before an operation can start at a work center due to the work center’s capacity utilization3. These time elements can be reduced by a percentage or a fixed value in the reduction strategy. References: 1: Reduction Strategy | SAP Help Portal(https://blog.sap-press.com/4-strategies-for-make-to-stock-production-with-sap-s4hana) 2: 4 Strategies for Make-to-Stock Production with SAP S/4HANA(https://blogs.sap.com/2022/03/22/highlights-for-manufacturing-in-sap-s-4hana-2021-part-2-production-planning-engineering-operations/) 3: Scheduling | SAP Help Portal(https://blogs.sap.com/2022/04/26/manufacturing-in-sap-s-4hana-cloud-planning-strategies/).
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
Create an object selection variant for priority-category-related alerts.
Assign the alert profile to the overall profile.
Create an object selection variant for production-planning-related alerts.
Assign the overall profile to the authorization profile.
The alert monitor in Advanced Planning allows you to monitor and analyze the planning situation and identify any problems or deviations from the desired state. To use the alert monitor, you need to configure the following elements:
Therefore, to set up the alert monitor, you need to assign the alert profile to the overall profile (B) and assign the overall profile to the authorization profile (D). Creating an object selection variant for priority-category-related alerts (A) or production-planning-related alerts © is not a configuration step, but a selection option in the alert monitor to filter the alerts by different criteria. References:
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
Scheduling agreement schedule line
Purchase Order
Planned Order
Production Order
A production planning run in Advanced Planning (PP/DS) is a process that optimizes the supply and demand situation for a set of materials and locations within a given planning horizon. The possible results of a production planning run are:
What does a line hierarchy in repetitive manufacturing represent?
A production line with more than one work center
A production line with prioritized work centers
A production line with a parallel sequence in the routing
A production line with an alternative sequence in the routing
A line hierarchy in repetitive manufacturing represents the structure of a production line that consists of multiple work centers. A line hierarchy is a master data object that defines the sequence and the relationship of the work centers that are involved in producing a material. A line hierarchy can be split into different levels, such as line segments, processing stations, or takt areas, to reflect the complexity and the variability of the production line. A line hierarchy can be used for planning and scheduling operations, controlling material flow, and monitoring production performance12.
The other options are not correct for the following reasons:
References:https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/48b24fbadbee4e0b9dae0e2b72762e68/db8151ba8ca14106bf037a1546cde6a9.html
https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/9231f9504a62eb5ee10000000a44538d.html
where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.
in the bill of material (BOM)
in the work centers
in the MRP controller
In the routing
in the production version
The system checks the master data selection settings during the creation of planned orders and production orders in the following places:
In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?
MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.
MRP assigns the capacity requirements automatically after the last scheduled order on a work center.
MRP creates the capacity requirements without checking the work center capacities.
MRP creates the capacity requirements only if the work center has sufficient capacity.
Infinite planning is a method of material requirements planning (MRP) that creates new orders without checking the capacity availability of the work centers. This means that the capacity requirements of a new order are created regardless of the existing capacity load or constraints of the work center. Infinite planning assumes that the required capacity canbe increased or adjusted as needed. Infinite planning is suitable for situations where the capacity supply is flexible and the demand is urgent or unpredictable. However, infinite planning can also result in capacity overloads or unrealistic schedules that need to be resolved later by capacity leveling or rescheduling. References: SAP S/4HANA Production Planning and Manufacturing II, Unit 1: Material Requirements Planning; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 77.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.
Increase the capacity supply in a time-phased interval.
Determine a time period with available capacity on the planning board.
Execute an infinite production planning run for the critical resources.
Reduce the planning Window.
Form optimum sequence to reduce setup times.
Which of the following elements does MRP take into account during net requirement
calculation? Note:
There are 2 correct answers to this question.
Forecast key figures
Safety Stock
Maximum stock level
Purchase orders
MRP (Material Requirements Planning) is a process that calculates the quantity and timing of material requirements based on the demand and supply situation. MRP performs a net requirement calculation for each material, which compares the available stock and the planned receipts with the requirements and the planned issues. MRP takes into account the following elements during net requirement calculation:
MRP does not take into account the following elements during net requirement calculation:
References: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 86; [SAP Help Portal: Net Requirements Calculation].
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question
Define the special procurement type inside the material master.
Change the item category of the phantom assembly in the bill of material •—' (BOM)
Define the special procurement type inside the BOM
Change the phantom item indicator for the phantom assembly in the bill of material (BOM)
A phantom assembly is a material that is not physically produced, but its components are directly consumed in the production of a higher-level material. To set up a material as a phantom assembly, you need to do the following steps:
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.
Work Center
Production Version
Material
plant
The Advanced Planning flag is a field that indicates whether a data object is relevant for planning with Production Planning and Detailed Scheduling (PP/DS) in SAP S/4HANA. PP/DS is a component of Advanced Planning that provides more precise and flexible planning capabilities for critical products and resources. You can set the Advanced Planning flag for the following data objects:
The production version (B) and the plant (D) are not data objects that can have the Advanced Planning flag. The production version is a master data object that defines the combination of a bill of material (BOM) and a routing or a production process model (PPM) for a material. The production version does not have a separate flag for PP/DS, but it inherits the flag from the material and the work center. The plant is an organizational unit that represents a physical location where materials are produced or stored. The plant does not have a flag for PP/DS, but it is assigned to a location in PP/DS that represents the geographical or logical grouping of plants for planning purposes. References:https://blogs.sap.com/2018/02/12/ppds-for-sap-s4hana-advanced-planning-a-powerful-planning-and-scheduling-tool/
https://learning.sap.com/learning-journeys/explore-integrated-business-processes-in-sap-s-4hana-/advanced-planning_ae824eb6-4bf8-4720-a48f-ba86929a14de
What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question
One-off events
Past quotation quantities
Past sales order quantities
Market intelligence
Past production planning quantities
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
Queue
Teardown time
Move time
Setup Time
The time element of midpoint scheduled operations that can be reduced by reduction strategy settings while dispatching are teardown time and setup time. Teardown time is the time required to dismantle the production equipment after the operation is completed. Setup time is the time required to prepare the production equipment before the operation is started. Both teardown time and setup time can be influenced by the reduction strategy settings, which define the percentage of reduction and the minimum duration for each time element. The reduction strategy settings can be maintained in the work center or the routing. The system applies the reduction strategy settings when dispatching the operations to the resources in the planning board or the product view. References: SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 32; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 81.
What will happen in the MRP run if you have created a new MRP-relevant material that
supports both in-house production and external procurement?
The MRP run assumes external procurement.
The MRP run assumes in-house production.
The MRP run does NOT consider the material; it has to be planned interactivelty
The MRP run plans the material only if a quotation has been maintained.
If you have created a new MRP-relevant material that supports both in-house production and external procurement, you need to specify the procurement type for the material in the material master record. The procurement type determines how the material is procured, either in-house, externally, or both. If you do not specify the procurement type, the MRP run does not consider the material, and it has to be planned interactively using the MRP Live app or the MD04 transaction. In interactive planning, you can manually assign a procurement type to the material and create the corresponding order proposals, such as planned orders or purchase requisitions. Alternatively, you can maintain a production version for the material, which defines the procurement type and the BOM and routing to be used for in-house production or external procurement. The production version can be assigned to the material in the material master record or in the MRP Live app or the MD04 transaction. The production version allows the MRP run to plan the material automatically based on the specified procurement type123. References: Procurement Type | SAP Help Portal, Production Version | SAP Help Portal, Material Requirements Planning with SAP S/4HANA, page 79-80.
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
Kanban
Material requirements planning
Backflushing
Production order release
If the available stock is zero and the discontinuation date is in the past, the material requirements planning (MRP) process will be affected. MRP will not create any planned orders or purchase requisitions for the discontinued component. Instead, it will create a discontinuation indicator in the MRP list and a discontinuation message in the exception message list. This will inform the planner that the component is no longer available and that a follow-up material should be used instead. References: [SAP Help Portal] - Discontinuation of Materials.
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
Move Time
Pick/pack time
Setup time
Float before production
Queue time
A routing operation is a step in the production process that defines the work center, the duration, and the sequence of the operation. A routing operation consists of several time elements that are used to calculate the operation start and finish dates, as well as the capacity requirements. The time elements that are part of a routing operation are:
The pick/pack time and the float before production are not part of a routing operation. The pick/pack time is the time required to pick the material from the storage location and pack it for delivery, which is usually part of the outbound logistics process. The float before production is the time buffer before the scheduled start date of the production order, which can be used to compensate for delays or changes in the production plan.
References: [Production Planning with SAP S/4HANA], pages 177-179; [SAP Help Portal: Routing Operation].
Generic Parent » Generic 1 pt
What is the purpose of collective orders?
To manage production orders for an entire finished product on multiple levels
To combine order management of co-products and by-products with the main product
To post production costs on a cost collector instead of the production order
To post any component withdrawal as single backflush with order confirmation
Collective orders are used to represent multilevel production structures for materials produced in-house, where the manufacturing order for the highest material in the structure automatically generates manufacturing orders for the semifinished products in the structure. This allows for an integrated view of the production process and avoids unnecessary placements in storage or removals from storage between production levels. Collective orders can consist of planned orders, production orders, or process orders, and each order has its own order number. Collective orders can be processed with or without automatic goods movements, depending on the business scenario. References: Collective Orders | SAP Help Portal, Collective Order | SAP Help Portal, Combined production order Vs Collective production order in SAP PP
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.
Note: there are 2 correct answers to this question.
Manual maintenance
100% check
First in First out (FIFO).
Simultaneous
Alternative item strategies are used to define how the system selects the alternative items in a BOM during the planning run or the order creation. The following alternative item strategies are available in SAP S/4HANA:
References:
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Note: There are 2 correct answers to this question
Production cost collector
Repetitive manufacturing profile
Routing
Production version
The work center that represents the production line for repetitive manufacturing is maintained in two places: the repetitive manufacturing profile and the production version. The repetitive manufacturing profile is a control parameter that defines the basic settingsfor repetitive manufacturing, such as the planning type, the backflushing method, the confirmation type, and the production line determination. The production version is a combination of a bill of material (BOM) and a routing or a rate routing that specifies how a material is produced. The production version also contains the work center that represents the production line for the material. The production version is assigned to the material master and is used in the planning and execution of repetitive manufacturing. References: Repetitive Manufacturing Profile | SAP Help Portal, Production Version | SAP Help Portal, Make-to-Stock Repetitive Manufacturing | SAP Help Portal.