New Year Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems Exam Practice Test

Page: 1 / 11
Total 110 questions

SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Question 1

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

Options:

A.

Service specification

B.

Overall limit (maximum value of all unplanned services)

C.

Service purchase order number

D.

Material master within service specification

E.

Vendor

Question 2

How can you confirm the working hours of different work centers for a single activity?

Options:

A.

Create multiple confirmations for the activity and use the appropriate work center for each confirmation

B.

Enter direct activity allocation assigning multiple work centers

C.

Enter multiple work centers within a single confirmation

D.

Assign multiple work centers to the activity

Question 3

How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question

Options:

A.

By searching for the status profile

B.

By searching via status selection profile

C.

By searching via status combination code

D.

By searching for the individual status

Question 4

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

Options:

A.

Scheduling and capacity category

B.

Scheduling and distribution key

C.

Control key of an activity

D.

Capacity planner group in the network header

Question 5

Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

Options:

A.

Individual overview capacity requirements

B.

Capacity load work center view

C.

Extended capacity evaluation

D.

Structure overview

Question 6

Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

Options:

A.

Document information records

B.

Internally processed activities

C.

Basic dates for activities

D.

Material components

E.

Relationships

Question 7

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

Options:

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Question 8

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Options:

A.

You can create several WBS elements per level.

B.

A new work breakdown structure must contain up to 10 levels.

C.

A WBS element of the new project can be assigned to a different project definition.

D.

WBS element can be a planning element, an account assignment element, and a billing element at the same time.

E.

The WBS structure can contain several level 1 WBS element,

Question 9

You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

Options:

A.

Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt

B.

. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt

C.

Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

D.

Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

Question 10

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

Options:

A.

You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

B.

You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

C.

You can always maintain the actual start and finish date of a WBS element

D.

You can only maintain the actual start of a WBS element if the finish date is not maintained

Question 11

Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

Options:

A.

You can map a project using only one WBS or one network.

B.

You can also represent a project using a WBS and one or more networks.

C.

You can create a project based on a Activity.

D.

You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.

Question 12

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.

You can create project coding mask X... event if there are project numbers beginning with X.

B.

The standard project definition must differ from the definition of the operative project.

C.

You can use only numbers for a project coding mask definition.

D.

You can use an indicator to determine that only coded project numbers may be used within the project system.

Question 13

What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question

Options:

A.

Confirm production order

B.

Stock transfer posting

C.

Generate purchase requisition

D.

Generate delivery

E.

Cancel goods issue

Question 14

The__________________that you specify when you create a project definition is unique for theentire project. Choose the correct answer.

Options:

A.

Plant

B.

Controlling area

C.

Company code

D.

Planning department

Question 15

What are valid procurement types for stock items? Note: There are 3 correct answers to this question

Options:

A.

Preliminary purchase requisition for WBS element

B.

Planned order

C.

Third-party order

D.

Purchase requisition and Reservation for WBS element

E.

Reservation for WBS element

Question 16

How can you grant individual authorization for WBS elements and networks?

Options:

A.

Define a user status to lock the business transaction Update Project.

B.

Set the system status to "Lock Master Data".

C.

Activate access control lists (ACL) for the user master record.

D.

Activate access control lists (ACL) for the project profile and the network profile

Page: 1 / 11
Total 110 questions