Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *
Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?
There are 2 correct answers to this question.
Response:
In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?
Please choose the correct answer.
Response:
Which of the following information regarding cost activity is not relevant for the calculation of planned costs?
Please choose the correct answer.
Response:
Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?
Please choose the correct answer.
Response:
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?
Please choose the correct answer.
Response:
Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response?
Please choose the correct answer.
Response:
What are the different options available for project stock?
There are 3 correct answers to this question.
Response:
Where can you define that a network is a "header-account assigned" or "activity-account assigned"?
You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason?
Please choose the correct answer.
Response:
What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?
Please choose the correct answer.
Response:
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:
Which combination allows you to assign the material components in one WBS element to different grouping WBS element?
There are 2 correct answers to this question.
Response:
Project System has its own Organizational structure, which can be a matrix structure.
Please choose the correct answer.
Response:
Which SAP standard item category always leads to direct procurement and a purchase requisition generated by the network?
Please choose the correct answer.
Response:
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?
Please choose the correct answer.
Response:
In which of the following ways Open PS allows you to exchange data directly with MS project?
There are 3 correct answers to this question.
Response:
Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?
Please choose the correct answer.
Response:
With reference to WBS scheduling, which of the following statements are FALSE?
Please choose the correct answer.
Response:
Which of the following determines the item category assigned in the sales documents?
There are 2 correct answers to this question.
Response:
How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities?
Please choose the correct answer.
Response:
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?
Please choose the correct answer.
Response:
Which type of reports allows you to choose the objects whose costs you want to analyze or call up an appropriate list and choose the period you want to evaluate?
Please choose the correct answer.
Response: