SAP Certified Associate - Organizational Change Management Questions and Answers

Question 1

What is the key benefit of capturing lessons learned towards the end of a cloud implementation?

Options:

A.

It facilitates the hand-over process of important project activities to the IT organization of the company.

B.

It helps to identify ad-hoc activities to foster high and sustainable user adoption after the go-live.

C.

It supports the project leadership team to identify the project team members who deserve special appreciation for their good work.

D.

It contributes to the organization’s capabilities to successfully handle future business transformations.

Question 2

The stakeholder analysis in a cloud project reveals that two important business leaders belong to the “opponents” category. What are your favorite strategies? Note: There are 2 correct answers to this question.

Options:

A.

Trying to reduce their influence on the project success

B.

Preventing opponents from forming an alliance against the project

C.

Working on changing their attitude towards the project

D.

Ignoring the opponents and focusing on the skeptics

Question 3

A repeated stakeholder analysis for the management team of an impacted business unit reveals that targeted communication activities for one opponent do not have the desired impact on the opponent’s attitude. What would you recommend as a next activity?

Options:

A.

Use financial incentives to motivate the opponent to visibly support the project and thus foster the opponent’s buy-in.

B.

Invite the opponent to the next steering committee meeting to discuss and challenge their negative perception of the project.

C.

Ask the project sponsor to get actively involved in stakeholder engagement activities targeted at the opponent.

D.

Provide specific enablement sessions to positively influence the opponent’s attitude.

Question 4

What are the special characteristics of SAP's organizational change management framework? Note: There are 3 correct answers to this question.

Options:

A.

It supports an agile way of working

B.

It is aligned with the SAP Activate implementation methodology

C.

It is only suitable for large-scale, complex cloud deployments

D.

It contains activities that help to enhance system performance

E.

It is targeted at fostering fast and sustainable user adoption

Question 5

What is the added value of change agents taking over the task to plan and execute local change management activities?

Options:

A.

It supports the adherence to the project milestones

B.

It fosters an attitude shift among skeptical change agents

C.

It helps to scale change management activities

D.

It reduces resistance among local managers

Question 6

What is the added value of a high-level change impact analysis? Note: There are 3 correct answers to this question.

Options:

A.

It reveals key project risks that can be integrated into the project's risk management at an early stage.

B.

It provides an initial systematic overview of the amount and the nature of the upcoming changes.

C.

It enables the project manager to identify opponents in highly impacted units and adjust the stakeholder analysis accordingly.

D.

It allows the change manager to derive appropriate activities, focusing the resources on key action areas.

E.

It delivers input for communication activities, making the implications of the project more tangible.

Question 7

Why is it important to map the new SAP roles and responsibilities to the business users impacted by a cloud implementation?

Options:

A.

It is the foundation for developing personas and defining stakeholder-specific communication activities.

B.

It allows the change manager to collect important information for developing the new operating model.

C.

It ensures that users are granted access only to the data, transactions, and system functionalities essential for their job roles.

D.

It contributes to reducing costs for both training activities and the IT infrastructure to be provided.

Question 8

Why is it recommended to prepare an interview guide for conducting change assessment interviews? Note: There are 3 correct answers to this question.

Options:

A.

It allows for efficient data collection by focusing on quantitative information

B.

It ensures that only the listed questions are asked during the interview

C.

It provides the structure for the interviews

D.

It helps to focus on the relevant key topics

E.

It serves as a cheat sheet in case the interviewer needs help

Question 9

Which skills and expertise should a change manager bring along to professionally support cloud projects? Note: There are 3 correct answers to this question.

Options:

A.

Excellent soft skills, such as being a good communicator, team player, and networker

B.

Broad technical expertise regarding the implemented cloud solution

C.

In-depth know-how of the best practice processes implemented with the cloud solution

D.

Comprehensive knowledge of the relevant change management concepts and tools

E.

Relevant methodological skills, such as facilitation, mediation, or problem-solving skills

Question 10

How is SAP's organizational change management framework connected with the SAP Activate methodology? Note: There are 2 correct answers to this question.

Options:

A.

The start of each change management activity is assigned to one specific SAP Activate phase

B.

Each change management dimension is assigned to a specific SAP Activate phase

C.

Some change management activities are executed in more than one SAP Activate phase

D.

The SAP Activate phases build the dimensions of the organizational change management framework

Question 11

What should be considered when developing personas? Note: There are 2 correct answers to this question.

Options:

A.

Finding the right level of detail, avoiding a too granular or too generic description of personas

B.

Involving representatives of the target group into the development of personas

C.

Aligning the persona descriptions with the employee representatives of the respective target groups

D.

Using a real person as an inspiration for the persona to make the persona as realistic as possible

Question 12

How is the cooperation between project management and change management during a cloud implementation organized?

Options:

A.

Project management focuses on the project tasks, change management on the cooperation within the project team.

B.

Project management focuses on the organizational level, change management on the individual and group level.

C.

Project management focuses on the objectives of the project, change management on the vision of the project.

D.

Project management focuses on the hard factors, change management on the soft factors.

Question 13

Which approach is suitable for conducting a communication needs analysis?

Options:

A.

Approaching managers or dedicated experts, because it is efficient and avoids unrealistic expectations

B.

Interviewing selected business users to explore their individual communication needs, because aggregating this data reveals important insights

C.

Setting up the analysis as a project activity, because it allows fast execution and fosters team spirit

D.

Conducting workshops in all impacted business units, because it gives the employees the feeling of being heard

Question 14

During a change network kick-off meeting, a change agent openly reports that he has beennominated by his manager against his will. How should the change manager react in this situation?

Options:

A.

Ask the change agent to find a substitute within his unit

B.

Clarify the issue with him bilaterally after the change network meeting

C.

Try to convince the change agent to take over the role anyway

D.

Request the change agent to leave the kick-off meeting

Question 15

What are the key elements of a user adoption strategy for an SAP cloud implementation? Note: There are 2 correct answers to this question.

Options:

A.

Agreed catalog of strategies to mitigate user adoption risks or issues

B.

Defined process for monitoring the selected user adoption indicators

C.

Agreed list of appropriate user adoption indicators before and after go-live

D.

Identified business stakeholders to be informed about the analysis results

Question 16

What are typical topics for a change assessment at the beginning of an SAP cloud implementation? Note: There are 3 correct answers to this question.

Options:

A.

The change culture of the company

B.

The scope for change management

C.

The cloud project's vision and expected benefits

D.

The company’s change management capabilities

E.

The assessment of the key stakeholders’ attitude towards the project

Question 17

What are possible options for setting up organizational change management in the project organization? Note: There are 3 correct answers to this question.

Options:

A.

As a separate project

B.

As a cross-topic

C.

As part of the functional sub-projects

D.

As a subproject

E.

As a staff unit

Question 18

Which general recommendations help to deliver change management successfully? Note: There are 2 correct answers to this question.

Options:

A.

Only use standardized tools and templates

B.

Calculate the return on investment (ROI) for change management activities

C.

Be user-centric and empathetic

D.

Establish trustful cooperation with project management

Question 19

What should a change manager keep in mind when identifying stakeholder groups?

Options:

A.

A business unit should be broken down into about five stakeholder groups

B.

The number of impacted employees should be documented

C.

Management teams are not listed as separate stakeholder groups

D.

The stakeholder identification is a one-time activity

Question 20

What does change enablement mean in the context of SAP cloud implementations?

Options:

A.

It refers to all tasks that support the project leadership team to learn how to deal with resistance during the cloud project

B.

It refers to all activities that help people to learn and adopt new SAP systems and processes in their working life

C.

It refers to all deliverables that support the project team to deliver change management during the cloud implementation

D.

It refers to all activities that upskill the impacted business leaders to handle organizational change management in their areas of responsibility

Question 21

How are users impacted by the implementation of an SAP cloud solution? Note: There are 2 correct answers to this question.

Options:

A.

They must adopt the new best-practice processes

B.

They must prepare for a long implementation process

C.

They must get accustomed to ongoing change

D.

They must customize the solution according to their specific needs

Question 22

What are success factors for the different dimensions of the change management framework? Note: There are 3 correct answers to this question.

Options:

A.

Regarding change realization, it is important to actively support the business units in the development of a new operating model.

B.

Regarding change strategy, it is important to fulfill the expectations towards change management.

C.

Regarding change leadership, it is important to establish stakeholder management as an ongoing activity.

D.

Regarding change effectiveness, it is important to use a balanced combination of change effectiveness measures.

E.

Regarding change communication, it is important to develop a compelling, comprehensive change story.

Question 23

The project leadership team agreed on the pulse check objectives, focus topics, target groups, and guiding principles. What are the next steps that must be executed to set up a pulse check? Note: There are 2 correct answers to this question.

Options:

A.

Plan the survey waves for the remaining project duration

B.

Involve employee representatives if required due to legal regulations

C.

Develop the questions and prepare the questionnaire in a survey platform

D.

Inform the steering committee about the time schedule for the pulse check

Question 24

What are the benefits of different communication channels for the change communication in an SAP cloud project?

Options:

A.

Using already existing channels reduces costs and effort, and establishing new channels helps to draw attention to the communicated content.

B.

Using already existing channels allows to communicate generic information, and establishing new channels helps to convey messages to younger users.

C.

Using already existing channels helps to point out what remains stable, and establishing new channels contributes to preventing an information overload.

D.

Using already existing channels allows a fast internalization of conveyed messages, and establishing new channels reduces the alignment effort with the project lead.