Halloween Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMP Project Management Professional (2024 Version) Exam Practice Test

Page: 1 / 170
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 1

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

Question 2

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

Options:

A.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert's availability within the organization on an as-needed basis.

C.

Develop the team member's capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Question 3

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Question 4

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

Question # 4

Options:

Question 5

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.

What should the project manager do?

Options:

A.

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead's functional manager.

Question 6

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Question 7

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Question 8

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Question 9

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

Options:

A.

Send out daily emails with the project status and task lists to all team members.

B.

Meet daily with the project team and include a monthly report on the risks and issues.

C.

Distribute a project newsletter that includes any project changes and required project information.

D.

Encourage collaboration on a daily basis, facilitating different communication channels.

Question 10

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

Options:

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

Question 11

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Question 12

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

Options:

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Question 13

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Question 14

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

Options:

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

Question 15

A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.

What should the project manager do to ensure team members are committed to project success?

Options:

A.

Control and follow the project's mam goals, budget, and schedule

B.

Plan regular virtual meetings to motivate and support the team.

C.

Meet in small groups and share information by email with the rest of the team

D.

Create a monthly report so everyone will be informed of the current status.

Question 16

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

Options:

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

Question 17

Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

Options:

A.

Ask the contractor to solve this problem because this is a contractual obligation.

B.

Terminate the contract and initiate a new one with a local contractor.

C.

Implement key performance indicators (KPIs) and convince the contractor to engage the team.

D.

Reassess continually to remove blockers for the team.

Question 18

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Question 19

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Question 20

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Question 21

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Question 22

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

Options:

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Question 23

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

Options:

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

Question 24

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

Options:

A.

Seek help from experts to support the team member in fixing the problem.

B.

Facilitate a session to reach an agreement with the team as a whole.

C.

Negotiate with the customer a delay in the project delivery.

D.

Accept the team's request to reassign the team member.

Question 25

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Assign a technical writer to the project.

D.

Develop a standard for document quality control.

Question 26

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

Options:

A.

Use the existing budget for executing the fallback plan and update the baseline.

B.

Add additional resources to the project to fast track certain activities and reduce delays.

C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.

D.

Communicate the delay to stakeholders and maintain the existing budget baseline.

Question 27

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Question 28

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

Question # 28

Options:

Question 29

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Question 30

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Question 31

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Question 32

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Question # 32

Options:

Question 33

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Question 34

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Question 35

A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.

What should the project manager do to keep the team performing as effectively as possible?

Options:

A.

Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,

B.

Transition the team from an agile approach to a predictive approach for better performance cantral.

C.

Provide the team with virtual collaboration software and training on the software to minimize disruption,

D.

Evaluate project performance and step in if performance decreases to. an unacceptable level,

Question 36

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

Options:

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

Question 37

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Question 38

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Question 39

A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.

What should the project manager do?

Options:

A.

Ask the team to outline their expectations and confirm with them the approach to use for knowledge transfer.

B.

Organize knowledge-sharing workshops and ask one of the senior team members to facilitate them.

C.

Ensure that formal email communication is used when more information is needed to understand the work done.

D.

Hire a technical writer to document the work completed to date and develop a handover document.

Question 40

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

Options:

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Question 41

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

Options:

A.

Invite the sales manager to the next sprint meeting to clarify requirements.

B.

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.

Request a meeting with the product owner to help clarify the user story.

Question 42

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.

B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.

Question 43

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options:

A.

30/40

B.

40/70

C.

30/70

D.

40/30

Question 44

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

Question 45

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

Options:

A.

Plan for continuous validation of the product.

B.

Discuss adding business scenario tests with the customer.

C.

Discuss adding additional test cases with the product owner.

D.

Add more test scenarios based on the issues found.

Question 46

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

Options:

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Question 47

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Question 48

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.

B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.

C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.

D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.

Question 49

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Question 50

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

Options:

A.

Escalate the team member's disruptive behavior to their functional manager.

B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.

C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.

D.

Request team members document their decisions independently and share with each other.

Question 51

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

Options:

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Question 52

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Question 53

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Question 54

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

Options:

A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.

B.

Specify the scope and features to be deployed in the contract clearly.

C.

Work very closely with the customer and third parties to meet their needs.

D.

Change the marketing and product management definitions to meet stakeholder needs.

Question 55

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Question 56

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Question 57

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

Options:

A.

Prioritize which backlog activities should be kept.

B.

Work on the backlog activities with fewer story points.

C.

Ask for more resources to clear the backlog activities.

D.

Assign an owner for each backlog activity and track progress.

Question 58

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Question 59

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Question 60

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Question 61

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

Options:

A.

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.

Remove the project team member immediately and assign the pending activities to other team members.

C.

Tell the customer that they do not have the authority to remove project team members.

D.

Ask the project team member to call the customer to apologize for their behavior.

Question 62

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

Options:

A.

Allow collaboration to smooth out communication between team members.

B.

Add collaboration tools to the communications management plan.

C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Question 63

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

Options:

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Question 64

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Question 65

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.

B.

Confirm with the team members that the functional manager is responsible for the delivery.

C.

Ask the product owner to clarify the roles and responsibilities of the project team.

D.

Inform the functional manager that task allocation is the responsibility of the product owner.

Question 66

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

Options:

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

Question 67

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Question 68

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

Options:

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Question 69

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

Options:

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

Question 70

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

Question 71

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

Question 72

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Question 73

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

Options:

A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.

Share weekly status reports with detailed information about the project and team performance.

C.

Submit performance reports and task assignments to keep the stakeholder informed.

D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.

Provide training to the team on emotional intelligence and status reporting techniques.

Question 74

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

Options:

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

Question 75

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

Options:

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Question 76

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

Options:

A.

Modify the project management plan and get approval from relevant stakeholders

B.

Add more resources to recover the schedule without making changes to the baseline.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Negotiate with the project sponsor immediately and establish a new project charter.

Question 77

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Study and determine the appropriate leadership style suitable for the team.

B.

Hire a project team leader who can influence the project team members.

C.

Schedule a meeting and communicate the performance concern to the team.

D.

Apply an agile approach to help improve team performance.

Question 78

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

Options:

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Question 79

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

Options:

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Question 80

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Question 81

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

scalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Question 82

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Question 83

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Question 84

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

Options:

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Question 85

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

Options:

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

Question 86

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

Options:

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Question 87

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

Options:

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

Question 88

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

Options:

A.

Propose implementing a new project management information system (PMIS).

B.

Request a meeting with senior management to escalate the situation

C.

Promote adoption of the communications management plan with the project team.

D.

Host a team-building event to develop team cohesion and improve communication

Question 89

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

Options:

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Question 90

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

Options:

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Question 91

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings

How should the project manager handle this moving forward?

Options:

A.

Ask that only key decision makers attend the project meetings.

B.

Update the project schedule to cater to this particular stakeholder

C.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

D.

Update the risk register to consider the possible project impacts

Question 92

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Question 93

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Question 94

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)

Options:

A.

Use the project's contingency budget

B.

Create a change request with the scope of the new internal projects.

C.

Influence the client to initiate a new project.

D.

Create a work breakdown structure (WBS) of the new scope with the internal projects

E.

Manage the quality of the delivery

Question 95

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

Options:

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Question 96

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

Options:

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Question 97

The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?

Options:

A.

Arrange a meeting with the managers and try to reach an agreement.

B.

Communicate with the project sponsor regarding the need to resolve the conflict between the managers.

C.

Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan

D.

Meet with both teams and their managers and try to figure out the root cause of the conflict

Question 98

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

Options:

A.

Contingency control in the project and rebaseline

B.

Mitigation control in the project

C.

Benefits management control in the project

D.

Integrated change control in the project

E.

Currency exchange rate

Question 99

In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?

Options:

A.

Let the developers focus on the refactoring work and discuss it in the retrospective

B.

Restate to the developers the importance of focusing and meeting the sprint goal.

C.

Praise the developers for their proactivity and focus on quality.

D.

Escalate the issue to the developers’ functional managers

Question 100

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Question 101

A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again

What should the project lead do next?

Options:

A.

Notify senior management of the issues and have them review the importance of agreements with the team

B.

Challenge the team to determine if the issues surfaced again because agreements were not followed

C.

Post the agreements in a conspicuous place where all of the team members can see them.

D.

Let the team self-organize and determine the best means to prevent the issues from occurring again

Question 102

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Question 103

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

Options:

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Question 104

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

Options:

A.

Hire a team of external users to perform acceptance testing on the product.

B.

Define a user focus group as external stakeholders with a high influence on outcomes

C.

Hire a consultant to perform a benefit analysis as an input to the project charter.

D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS

Question 105

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

Question 106

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Question 107

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change is

acceptable

Question 108

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.

Team A as they have calculated fewer story points than team B.

B.

Team B as they have calculated more story points than team A

C.

The team that completes the most stories selected from the sprint backlog

D.

The team with the least amount of defects in their deliverables

Question 109

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

Options:

A.

Exclude the activities from the roadmap

B.

Encourage working in pairs and knowledge sharing

C.

Teach the entire team the new skill.

D.

Facilitate a training event with an external trainer

E.

Increase the time estimates on the activities that require such abilities

Question 110

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Question 111

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Question 112

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.

Ensured the risk tolerance of the company was property updated

B.

Implemented the communications management plan properly

C.

Implemented the stakeholder engagement plan correctly.

D.

Provided a proper risk response

Question 113

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

Options:

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Question 114

Drag the communication event on the left to the mam subject discussed during the event on the right.

Question # 114

Options:

Question 115

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

Question # 115

Options:

Question 116

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Question 117

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

Options:

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

Question 118

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experience

to build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Question 119

During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?

Options:

A.

Defined the expected agile team contribution in the creation of the backlog.

B.

Assessed the capabilities of the agile team and planned for the required training

C.

Defined the team ground rules and shared project vision.

D.

Communicated project vision and sprint goals clearly to the team

Question 120

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.

Use soft skills to convince the project sponsor to approve the new budget estimate

Question 121

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

Options:

A.

Share this opportunity with another project

B.

Establish a contingency reserve to support the opportunity

C.

Further monitor the opportunity

D.

No more action is required

Question 122

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

Options:

A.

Conduct a stakeholder analysis.

B.

Reinforce team communication.

C.

Update the project management plan with the new timeline

D.

Adopt an incremental approach

E.

Leverage work between team members

Question 123

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

Options:

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

Question 124

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

Options:

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Question 125

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Question 126

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

Options:

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Question 127

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

Options:

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Question 128

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?

Options:

A.

Schedule meetings with the customer to determine their ability to support multiple incremental deliveries

B.

Work with the agile team to schedule the incremental deliveries to enable delivery

of business value sooner to the customer.

C.

Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries

D.

Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.

Question 129

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

Options:

A.

Start an audit of the vendor's processes and procedures

B.

Review lessons learned from previous projects with this vendor

C.

Make a detailed analysis on vendor issues during the project

D.

Execute a contingency plan to address the issue with the vendor

Question 130

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

Options:

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Question 131

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Question 132

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

Question # 132

Options:

Question 133

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

Options:

A.

Ask the project team to perform the modifications since the project budget and schedule can support them.

B.

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested

C.

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.

D.

Analyze the reason for the gap in understanding with both sides and negotiate a solution

Question 134

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Question 135

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a prioritized backlog and define iteration review sessions with stakeholders

B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.

Schedule a daily meeting to review team performance and impediments

D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Question 136

A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.

What can the project manager do to help increase the team's motivation and engagement with the project?

Options:

A.

Review sprint progress with the project team members

B.

Set up one-on-one meetings with the project team members

C.

Review sprint planning procedures with the project team members

D.

Perform a sprint retrospective with the project team members

Question 137

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

Options:

A.

Request the project management office (PMO) for a team of mentors.

B.

Allocate time to mentor the team.

C.

Update the issue log.

D.

Identify any training gaps

Question 138

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

Options:

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Question 139

The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?

Options:

A.

Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest.

B.

Invite the executive to the project's meeting space to determine if the project information radiators meet their needs

C.

Reach out to the project management office (PMO) for status report templates and provide project updates in that format

D.

Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments

Question 140

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Question 141

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Question 142

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Question 143

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

Question 144

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Question 145

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

Question # 145

Options:

Question 146

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Question 147

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

Options:

A.

Complexity and the cost of development

B.

Industry trends and the technical approach

C.

Cost of delaying some features against business value

D.

Reusing components from another product

E.

Length of time each feature has been on the backlog

Question 148

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Question 149

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

Options:

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Question 150

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

Options:

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Question 151

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.

Make sure the project team is aware of all agile techniques

B.

Skip the training because the team already understands agile

C.

Ensure the team has a common understanding of agile

D.

Teach one agile methodology fully and completely

Question 152

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

Options:

A.

Revisiting the project management plan to ensure deliverables are on time

B.

Increasing the frequency of project update meetings to keep stakeholders informed

C.

Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders

D.

Reviewing the business case and identifying gaps within scope

Question 153

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Question 154

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder's understanding during the kick-off meeting

Question 155

A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information

How should the project manager handle this situation?

Options:

A.

Apply lean manufacturing to limit the team’s work

B.

Increase retrospectives to deliver results fast

C.

Make work visible using kanban boards.

D.

Incorporate small batches of work into the project

Question 156

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Question 157

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Question 158

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Question 159

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

Question # 159

What should be the priority order in the product backlog?

Options:

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Question 160

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

Options:

A.

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.

It is a record that shows the number of attendees in the meeting

D.

It is a document that is registered within the lessons learned register

Question 161

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Question 162

A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

Options:

A.

Acquire project resources from the new country to mitigate the risk of uncertainty

B.

Evaluate the environmental and regulatory factors and identify high-level risks and assumptions

C.

Identify and monitor the risks closely since the company does not have lessons learned for this country.

D.

Ensure that project sponsors are in agreement on the project deliverables and timeline during the project

Question 163

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Question 164

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Question 165

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished

What should the project manager have done differently?

Options:

A.

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint

B.

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments

C.

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

D.

Arranged an online session on the integration concept and suggested tools to the teams

Question 166

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

Options:

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project's changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Question 167

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.

Analyze both projects to determine the most effective use of common resources

B.

Use resource optimization to justify requesting more resources for the critical project

C.

Provide schedule optimization training to the project teams to improve their skills.

D.

Apply fast-tracking techniques to compress the schedule of the critical project

Question 168

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Question 169

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

Options:

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

Question 170

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

Options:

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

Question 171

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

Options:

A.

Allow project B's leader to continue building relationships.

B.

Talk with project B's leader to discuss possible impacts to both projects.

C.

Tell project A's team member to ignore project B's leader.

D.

Ensure project A's team member can finish the work committed to project A.

Question 172

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

Options:

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Question 173

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

Options:

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Question 174

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

Question 175

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

Options:

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Question 176

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

Options:

A.

Have a one-on-one discussion with each team member to emphasize their individual

talents.

B.

Document the behavior of the team members and highlight it during their performance

reviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

Question 177

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

Options:

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer's priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

Question 178

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

Options:

A.

Communicate the delivery dates twice a week to the team members to ensure timely

delivery.

B.

Set up review sessions with each of the team members to identify the root cause of

delays.

C.

Mentor the team members to work in a remote work environment to ensure

productivity.

D.

Talk to the resource managers regarding the delay and request additional resources

Question 179

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assess

progress.

B.

Set up a feedback session with the product owner once a week so they can assess

progress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner's functional manager to a feedback session to escalate the

issue.

Question 180

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

Question 181

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Question 182

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

Options:

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Question 183

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Question 184

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project

status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for

incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Question 185

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.

Update the risk register and implement the approved risk response plan for quality

deviations.

B.

Identify the resources that were responsible for the deliverable and request a team

development plan.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the

corrective actions.

D.

Submit a change request to update the project quality requirements for the involved

project deliverable.

Question 186

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Question 187

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Question 188

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.

B.

Commit each team member's time and deliverables and aim for overall project

completion.

C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question 189

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

Options:

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

Question 190

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Question 191

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk

B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices

D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update

Question 192

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Question 193

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

Options:

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Question 194

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Question 195

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.

Question 196

A key project stakeholder does not attend any of the project meetings and is

providing false information that the project team is not delivering on time. What should the

project manager do to address this situation?

Options:

A.

Create a new communication artifact for the key stakeholder.

B.

Email the latest status report to the key stakeholder.

C.

Share the meeting recordings with the key stakeholder.

D.

Discuss communication needs with the key stakeholder.

Question 197

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

Options:

A.

Discuss the concerns with the project sponsor and modify the project charter to include

more budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Question 198

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Question 199

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

Options:

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

Question 200

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

Options:

A.

Request that the vendor provides a manual with all required knowledge

B.

Implement retrospectives with the vendor to gather the required knowledge

C.

Submit a change request to extend the vendor's contract to provide formal training for the team

D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained

Question 201

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

Options:

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Question 202

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Question 203

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

Options:

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Question 204

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

Options:

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

Question 205

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

Options:

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Question 206

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Question 207

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Question 208

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

Options:

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Question 209

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

Options:

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Question 210

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

Options:

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Question 211

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.

Update the stakeholder register.

B.

Refer to the resource management plan.

C.

Consult the project sponsor.

D.

Modify the statement of work (SOV).

Question 212

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

Options:

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders to

participate.

C.

Ensure that lessons learned are considered as part of the project schedule

decomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on other

projects.

Question 213

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

Options:

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn't be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

Question 214

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

Options:

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

Question 215

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Question 216

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

Options:

A.

Update the schedule to reflect the holidays and share the workload among offices to

mitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during the

holiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate schedule

slippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of the

delayed completion.

Question 217

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Question 218

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Question 219

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Question 220

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

Options:

A.

US$650,000

B.

US$452,500

C.

US$547,500

D.

US$582,500

Question 221

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.

Inform executive management that the customer is made aware of the status during

the sprint demo.

B.

Prepare a weekly status report and share it with executive management every week.

C.

Inform executive management about agile principles and processes that are followed

in the project.

D.

Ask the team to prepare and share the status report with executive management every

week.

Question 222

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Question 223

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

Options:

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Question 224

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Question 225

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.

C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.

Question 226

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Question 227

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

Options:

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Question 228

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Question 229

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Question 230

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.

Meet with the team member and search for the root cause of their behavior.

Question 231

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new team

members.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Question 232

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Question 233

A customer asks the project manager about opportunities to create business value.

What should the project manager do first in order to provide the customer with an appropriate

response?

Options:

A.

Examine the business value throughout the project.

B.

Ask the team to organize a spike to identify more value.

C.

Meet with the product owner to review the backlog.

D.

Meet with the sponsor to review the business case.

Question 234

A project manager is leading a project that is in the execution phase. During a team

meeting, the project manager realizes that there are two team members who lack the

technical skills required for some of the upcoming tasks.

What should the servant leader project manager do next?

Options:

A.

Recommend to the team members to upskill themselves on the requirements for the

project.

B.

Discuss with the human resource (HR) manager about the possibility of changing team

members.

C.

Inform the sponsor about a possible delay due to the lack of skills in the team.

D.

Explore a training program that is within the project budget for the team members.

Question 235

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

Options:

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.

Remind the team frequently that the project must be delivered on time and within budget

C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Question 236

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of reaching the agreed deadlines and value.

B.

Request to coach the team to ensure motivated project team members are on board.

C.

Update the project schedule with a buffer to reflect the expected delays being incurred

by the team.

D.

Suggest to the teams to limit the scope of work per iteration so they will start to deliver

more reliably.

Question 237

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Options:

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatory

requirements.

D.

The project manager must follow their employer's organizational process assets

(OPAs).

Question 238

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

Options:

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

Question 239

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

Question 240

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

Options:

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the quality

management plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Question 241

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

Options:

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.

B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

Question 242

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

Question 243

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Question 244

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.

Change management plan

B.

Schedule management plan

C.

Scope management plan

D.

Cost management plan

Question 245

A government agency is developing a new connectivity policy. The assigned project

manager is a famous economist with international recognition. The team is eager to work with

the project manager, but feels intimidated. The project manager realizes that a junior

economist, whose tasks are behind schedule, is especially intimidated by the situation.

What should the project manager do first?

Options:

A.

Evaluate the performance of the junior economist in the upcoming months.

B.

Reassign some of the junior economist's tasks to other economists.

C.

Request to replace the junior economist with a more experienced economist.

D.

Consider organizing paired work sessions for the junior and senior economists.

Question 246

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.

Redefine the communications management plan

B.

Develop an integrated change management plan

C.

Document the risk in the project risk register

D.

Review the scope defined in the project charter

Question 247

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Question # 247

Options:

Question 248

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Question 249

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Question 250

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Question 251

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Options:

A.

Reinforce the value of documenting and approving all change requests and ask the

customer to issue these through the agreed channels.

B.

Organize a meeting to mediate the relationship between the customer and the team

member to ensure no feelings are hurt.

C.

Ask the customer to email all requests directly to you and you will ensure they are

actioned by the correct team member.

D.

Explain to the customer that the team member was just trying to help and the changes

can be reverted if necessary.

Question 252

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

Question # 252

Options:

Question 253

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Question 254

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor and request extra time and budget to obtain

the component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to the

performance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) and

relevant stakeholders to identify alternatives to address the problem.

Question 255

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

Options:

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.

B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.

D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.

Question 256

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Question 257

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Question 258

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Question 259

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Question 260

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Question 261

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Question 262

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

Options:

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Question 263

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Question 264

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Question 265

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.

B.

Asked stakeholders not to voice their opinions during the meeting.

C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.

D.

Reinforced that higher-level management has the decision power.

Question 266

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Question 267

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

Options:

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Question 268

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

Options:

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Question 269

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

Options:

A.

Risk register

B.

Project schedule

C.

Change request

D.

Issue log

Question 270

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Question 271

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Question 272

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned

B.

Meet with the technical lead to review the sprint plan

C.

Meet with the product owner to confirm the minimum viable product (MVP) option

D.

Meet with the project team and reprioritize the backlog

Question 273

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

Options:

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Question 274

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

Options:

A.

Submit a change request to adapt the objectives of the project to the current situation

B.

Ask the scrum master to refine the user stones to improve the team members' understanding

C.

Find and provide training to the project team members who do not have the required skills

D.

Extend the duration of standup meetings to include skill transference from trained to untrained members

Question 275

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Question 276

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Question 277

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

Options:

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on the

project variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Question 278

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Question 279

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for the

decision.

Question 280

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Question 281

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Question 282

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

Options:

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Question 283

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Question 284

A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation

What should the project manager do?

Options:

A.

Communicate the ground rules, principles and reporting methods to the project stakeholders

B.

Penalize the project team lead for not updating the project documentation properly.

C.

Review this issue with the team lead for possible ways to resolve this situation

D.

Issue guidance to the team member about reporting directly to the project manager

Question 285

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Question 286

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

Options:

A.

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.

Update the acceptance criteria documentation to clearly reflect what was approved.

C.

Review the new requirement and update all the stakeholders accordingly.

D.

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Question 287

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.

Update the risk register in order to add the issue.

B.

Review the issue log regarding the concern

C.

Revise the benefits management plan

D.

Assess the repository to check for inconsistencies.

Question 288

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Question 289

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Question 290

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.

Propose using a compliance review board that will be responsible for approving all

product features prior to their release to the public.

B.

Liaison with the compliance group, making them responsible for understanding the

requirements and keeping them prioritized in the backlog.

C.

Meet with the compliance team and make sure that their requirements are covered in the

definition of done (DoD) for each story.

D.

Ensure that the peer review process also covers compliance requirements, creating a

second layer of security for the project.

Question 291

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Question # 291

Options:

Question 292

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Question 293

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Question 294

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute to

projects.

B.

Assign employees to agile projects so they can quickly adjust to the new approach.

C.

Train all employees in agile approaches.

D.

Shift the way the company views, reviews, and assesses employees.

Question 295

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Question 296

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

Options:

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Question 297

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Question 298

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

Options:

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Question 299

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Question 300

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

Options:

A.

Colocate the team members

B.

Perform team-building activities

C.

Review and reassign tasks

D.

Revisit the communications management plan

Question 301

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Question 302

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Question 303

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client is

not impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprint

review meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance model

and escalation path.

Question 304

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Question 305

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Question 306

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Question 307

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Question 308

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Question 309

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Question 310

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Question 311

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Question 312

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Question 313

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Question 314

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

Options:

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

Question 315

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Question 316

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Question 317

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.

Question 318

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

Options:

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

Question 319

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

Options:

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Question 320

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Question 321

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

Options:

A.

Work more closely with the agile team to eliminate the need for progress reports

B.

Record this in the issue log and find a resource to produce the reports

C.

Produce the progress reports on their own

D.

Engage a new resource to produce the progress reports

Question 322

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Question 323

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

Options:

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Question 324

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Question 325

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

Options:

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Question 326

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Question 327

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Question 328

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

Question 329

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Question 330

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

Options:

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

Question 331

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Question 332

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Question 333

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.

B.

The team productivity is higher; therefore, more value is delivered,

C.

The cost is reduced: therefore, the total value delivered is higher.

D.

The risk is significantly reduced; therefore, more value Is delivered.

Question 334

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Question 335

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Question 336

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

Options:

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

Question 337

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Question 338

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Question 339

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Question 340

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

Options:

A.

Create a risk probability matrix to address the incompatibility.

B.

identify an alternative component in case of incompatibility.

C.

Use the contingency fund to redesign the interface if it is incompatible,

D.

Require the vendor to redesign the incompatible component to fit the system.

Question 341

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

Options:

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Question 342

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Question # 342

Options:

Question 343

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Question 344

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Question 345

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

Options:

A.

Decrease the scope of the portfolio and send new solutions to the customer.

B.

Deliver a schedule with the portfolio timeline and delivery to the customer.

C.

Adopt an incremental cycle of delivering value to the customer.

D.

Prepare deliveries with more details to satisfy the customer.

Question 346

Drag the technical practices on the left to the scenario on the right.

Question # 346

Options:

Question 347

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.

What should the project manager do?

Options:

A.

Add the feature to the supplier's requirement list so they can deliver it.

B.

Ask the supplier to accommodate the additional scope under the current agreement.

C.

Ensure the project team understands the agreement and contract in place with the supplier.

D.

Monitor the work the business analyst is performing to avoid scope creep.

Question 348

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Question 349

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

Options:

A.

Escalate the issue to the project sponsor and seek assistance.

B.

Engage the project stakeholder and ensure all requirements are captured.

C.

Review the stakeholder engagement plan and communication strategy.

D.

Review the product requirements and update the stakeholder register.

Question 350

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Question 351

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Question 352

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

Options:

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

Question 353

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

Question 354

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

Options:

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Question 355

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

Options:

A.

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

Question 356

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change

Question 357

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

Options:

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Question 358

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Question 359

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

Options:

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Question 360

A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?

Options:

A.

Release plan Sy

B.

Product roadmap

C.

Kanban board

D.

Burndown chart

Question 361

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

Options:

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Question 362

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Question 363

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

Options:

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Question 364

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

Options:

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Question 365

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Question 366

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Question 367

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

Question 368

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Question 369

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Question 370

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

Options:

A.

Train the new team member in the predictive project management approach.

B.

Acknowledge that hiring this new employee is a risk to the existing team

C.

Set expectations with the new team member and explain what is needed

D.

Meet with all team members and explain the new employee's position.

Question 371

A project manager is assigned to a strategic communication project that involves

subject matter experts (SMEs), interns, and new recruits. The project manager discovers

that the project is not gaining much traction due to knowledge gaps from the interns. The

budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two)

Options:

A.

Identify the sources and specifics of the knowledge gap from the interns and new

recruits.

B.

Hire more SMEs and inform the human resources manager to lay off the

nonperforming interns and new recruits.

C.

Initiate a project change request for additional budget to train the interns and new

recruits.

D.

Ignore the issues with the project and try to deliver the project successfully without

asking for training funds.

E.

Put the interns and new recruits into groups and assign a SME as a mentor.

Question 372

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

Options:

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Question 373

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Question 374

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Options:

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Question 375

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Question 376

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Question 377

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Question 378

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Question 379

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

Options:

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Question 380

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Question 381

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Question 382

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?

Options:

A.

Ask the team member to complete as much as they can now.

B.

Ask the team member to work with their peers to knowledge share

C.

Ask the team member to identify their specialist tasks

D.

Ask the team member to host a special team meeting.

Question 383

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Options:

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Question 384

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Question 385

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then share

it with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agile

approach in the upcoming project.

C.

Make a request to human resources for new team members who have agile

experience.

D.

Ask the project sponsor to change the approach back to predictive as that is the

team’s strength.

Question 386

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

Options:

A.

Invest in developing the team's emotional intelligence.

B.

Ask the unmotivated team member to take a short leave.

C.

Reduce the number of daily and retrospective meetings.

D.

Send the unmotivated team member to another team.

Question 387

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Question 388

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Question 389

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Question 390

A company is planning a digitization project. Which action should the project

manager take first when defining the project scope?

Options:

A.

Assess the current state process to define the scope of the digitization.

B.

Digitize the current state process exactly as defined.

C.

Redefine the current state process to scope the supporting software.

D.

Develop the software that will support the current state process.

Question 391

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Question 392

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Question 393

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

Options:

A.

Send out a questionnaire to all users regarding the most useful features.

B.

Embed a feedback form into the system for users to respond.

C.

Interview a sampling of users to obtain the usage data.

D.

Build the functionality in the software to collect the operational usage data.

Question 394

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Question 395

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Question 396

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Question 397

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

Options:

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Question 398

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

Options:

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Question 399

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.

Start the project and add any uncertainty that arises to the risk register.

B.

Dissolve the virtual team and build a colocated team.

C.

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.

Build a culturally neutral team that will not be affected by cultural differences.

Question 400

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Question 401

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.

High-level product backlog

B.

Key performance indicators (KPls)

C.

Product vision

D.

Schedule performance indexes (SPIs)

E.

Product roadmap

Question 402

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Question 403

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

Options:

A.

Add the issue to the issue log and determine the corrective action.

B.

Create a fishbone diagram to determine the root cause for the misunderstanding.

C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.

D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.

Question 404

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Question 405

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

Options:

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Question 406

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

Question 407

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Question 408

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Question 409

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?

Options:

A.

Request additional budget to recruit more developers.

B.

Lower the recruitment criteria.

C.

Log the issue in the issue log.

D.

Analyze the impact and inform the stakeholders.

Question 410

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

Options:

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

Question 411

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Question 412

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

Options:

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Question 413

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

Options:

A.

Involved the customer more in the planning process for the project, and ensured

agreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Question 414

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Question # 414

Options:

Question 415

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Question 416

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Question 417

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Question # 417

Options:

Question 418

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Options:

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Question 419

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Question 420

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Question 421

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

Options:

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.

Question 422

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Question 423

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

Options:

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer's needs

D.

Allocate resources to work on the new feature immediately to complete the request

Question 424

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

Options:

A.

Reaffirm the required project obligations directly with the team member. oy

B.

Ask the team member to explain the reason for the absences.

C.

Assess the impact of the team member's absence on the task involved.

D.

Send a formal letter to the team member stating that their absences are noted.

Question 425

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Options:

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Question 426

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

Options:

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Question 427

A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?

Options:

A.

Brainstorming

B.

Meetings

C.

Regression analysis

D.

Expert judgment

Question 428

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

Options:

A.

Use a servant leader approach.

B.

Assume the functional manager role.

C.

Perform the project sponsor activities.

D.

Act as the project owner.

Question 429

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

Options:

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

Question 430

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

Options:

A.

Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.

B.

Create the project management plans with the project team and share the documents with the stakeholders.

C.

Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.

D.

Adapt the project management plans and documents from previous executed projects in order to save time.

Question 431

A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?

Options:

A.

Talk to the team member to determine why their performance changed.

B.

Talk to the team member and a human resources (HR) representative.

C.

Talk to the team member's manager to provide more training.

D.

Talk to the project lead and ask them to allocate less demanding tasks.

Question 432

Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?

Options:

A.

Prepare a user story to handle the change and assign it to the next iteration.

B.

Escalate to the product owner and cancel the upcoming iterations.

C.

Update the risk-prioritized backlog with the strategic change.

D.

Schedule a meeting with the team to assess the impact of the change.

Question 433

A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?

Options:

A.

Iterative scheduling

B.

Three-point scheduling

C.

Parametric scheduling

D.

Analogous scheduling

Question 434

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

Options:

A.

Product roadmap

B.

User stories

C.

Business requirements document

D.

Product backlog

Question 435

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

Options:

A.

Reschedule on-site training to online sessions.

B.

Create a risk and assign remediation actions.

C.

Cancel all of the on-site training sessions.

D.

Document the project issue and provide options.

Question 436

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

Options:

A.

Reach an agreement with the team on how to handle the situation.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Convince the team member not to leave until the project is completed.

Question 437

A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.

How can the project manager address this challenge to assure outsourced vendors deliver?

Options:

A.

Review the coordination and communication costs with the supplier.

B.

Develop a new strategy for communication and management of resources.

C.

Review the risk management plan for the mitigation activities.

D.

Submit a change request to increase the contingency budget.

Question 438

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

Options:

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

Question 439

A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.

What should the project manager do?

Options:

A.

Ensure that people care about each other and work effectively together through effective team management.

B.

Meet with the team to discuss the correct, expected behavior in stressful situations and start practicing it.

C.

Establish a productive environment where all team members can assist one another with the workload.

D.

Create an environment of respect and fairness so the team can increase their project performance in stressful situations.

Question 440

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

Options:

A.

Inform team B of the dependency and ensure that the deliverable is planned.

B.

Make team Aa part of team B and ensure that the deliverable is ready.

C.

Request team B to immediately start this activity and deliver to team A.

D.

Ask team B to focus on their backlog and deliver based on their priority,

Question 441

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Options:

A.

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Question 442

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

Options:

A.

Support the team in identifying the area of development and address the gap.

B.

Dissolve the team and include the team members in other existing teams.

C.

Identify the struggling team members and move them out of the team.

D.

Set up a clear expectation that the team is to deliver as in their previous projects.

Question 443

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

Options:

A.

Travel to the development team's office to push the schedule.

B.

Set up a meeting with key stakeholders to clarify requirements.

C.

Escalate to the project steering committee and request additional time.

D.

Create prototypes with the development team to confirm requirements.

Question 444

Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Set up a team building event to bring synergy back to the project team.

B.

Adjust the project manager's management style to better fit senior team members.

C.

Ask for advice on how to be a better mentor to these team members.

D.

Meet daily with each senior team member to monitor project status.

Question 445

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Question 446

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Options:

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Question 447

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two

projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.

What kind of leadership style should the project manager utilize for the current project?

Options:

A.

Transformational

B.

Interactional

C.

Laissez-faire

D.

Charismatic

Question 448

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

Options:

A.

Assess and prioritize the impact of the new law on the project plan.

B.

Update the project plan because the law is an obligation for the project.

C.

Minimize the scope to catch the cost and schedule baseline.

D.

Meet the sponsor to ask for additional time and budget increase.

Question 449

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?

Options:

A.

Feedback from the project sponsor

B.

Agreed-upon key performance indicators (KPIs)

C.

Input from project stakeholders

D.

Competencies of team members

Question 450

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?

Options:

A.

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.

B.

Include the project stakeholders’ needs while planning the project communications strategy.

C.

Designate a team member to respond to the emails from these stakeholders.

D.

Include the stakeholders’ emails in all of the project status communications.

Question 451

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Options:

A.

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.

B.

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.

C.

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.

D.

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.

Question 452

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

Options:

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

Question 453

A company is working on a project to develop an integration of their existing systems. There are known issues in production.

What should the project manager do?

Options:

A.

Identify and remove impediments and mitigate the risks.

B.

Ensure the product owner reviews requirements with the team.

C.

Include acceptance criteria in the definition of done (DoD).

D.

Review the quality control processes and procedures.

Question 454

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

Options:

A.

The customer's requirements should have been captured in order to meet the customer's standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer's requirements should have been captured and modified to meet the supplier’s standards.

Question 455

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

Options:

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

Question 456

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

Options:

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client's performance parameters.

D.

Established meetings with the client throughout the project phases.

Question 457

A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequate

authorization to make the decision themselves but is not quite sure.

What should the project manager do next?

Options:

A.

Use the project contingency and implement the change without charging the customer, since the customer's satisfaction is top priority.

B.

Exploit this change opportunity and calculate the cost, risk, and time, then add a reasonable margin and submit to the customer.

C.

Use the Perform Integrated Change Control process and submit this to the change control board (CCB) for approval.

D.

Keep the change pending and decide to take this up as part of final settlement at the end of the project.

Question 458

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

Options:

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Question 459

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

Options:

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Question 460

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

Options:

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Question 461

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.

Assign the task to someone else on the team.

B.

Discuss it with the team member in confidence.

C.

Discuss this matter during the project meeting.

D.

Include this item in the risk register.

Question 462

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?

Options:

A.

Implement and establish an agile framework for the project.

B.

Hire a team of contractors for agile project delivery.

C.

Define detailed work instructions for agile project delivery.

D.

Negotiate special arrangements for an agile pilot project.

Question 463

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as

a whole is low, especially in terms of group activities.

What should the project manager do?

Options:

A.

Negotiate for new team members.

B.

Review and update the communications management plan.

C.

Review and reassign team assignments.

D.

Facilitate communication and team building.

Question 464

A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.

However, that tool is not available in one team member's country.

How should the project manager deal with this situation?

Options:

A.

Contact the project sponsor to have the team member removed from the project.

B.

Ask the team member to move to another location where the tool is available.

C.

Start the project and use email to communicate with the team member until the tool is available.

D.

Investigate alternative tools for virtual meetings that are available to all team members.

Question 465

A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.

What can the project manager do to gain the support of the stakeholder?

Options:

A.

Ask the stakeholder for a meeting to review the project's charter and project management plan.

B.

Disregard the stakeholder's concerns and continue following the project management plan to execute the project.

C.

Hold a training workshop to educate the stakeholder about project management best practices.

D.

Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buy-in.

Question 466

A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?

Options:

A.

Divide the allocated budget by the number of work packages and verify that each work package can be completed within the allocated budget.

B.

Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.

C.

Create a budget burndown and a scope burnup and then verify that the project scope is completed before the allocated budget is depleted.

D.

Fund each work package in the order of its importance and shift any remaining scope from nonfunded work packages to funded work packages.

Question 467

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?

Options:

A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.

B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.

C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

D.

Foster stakeholder participation by engaging them early on the backlog discussions.

Question 468

In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests

that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.

What should the project manager do first to meet the product leader's expectations?

Options:

A.

Change the project charter to indicate that the approach will be different.

B.

Inform the product leader that they must wait until the end of the project.

C.

Meet with the software team to review the possibility of monthly milestone reviews.

D.

Modify the project management plan to use an agile framework to incorporate milestones.

Question 469

A project manager holds periodic progress review meetings to discuss issues. What should the project manager do first on the agenda?

Options:

A.

Produce lessons learned documentation.

B.

Elaborate the risk mitigation strategy and risk register.

C.

Formulate project management plan integration.

D.

Update resolution approaches and action assignments.

Question 470

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

Options:

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

Question 471

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

Options:

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Acquired more than one resource skilled in each component.

D.

Facilitated cross-functional knowledge transfer during the project.

Question 472

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

Options:

A.

Informal written communication, such as a friendly reminder

B.

Formal written communication, such as an email with a copy sent to the manager

C.

Informal verbal communication, such as a conversation

D.

Formal verbal communication, such as a conversation at the end of the sprint retrospective

Question 473

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

Options:

A.

Escalate the issue of the additional requirements to the executive leadership team.

B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).

C.

Implement all the requirements the customer has requested.

D.

Adjust the scope baseline and schedule baseline accordingly.

Question 474

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.

What should the project manager do?

Options:

A.

Replace the members with new members who understand the system.

B.

Encourage the team members to make changes directly in the system.

C.

Ask the team to read through all of the available system documents.

D.

Encourage the team to hold a knowledge-sharing session in each iteration.

Question 475

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Question 476

A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings

were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they

feel it is a waste of time.

What should the project manager do?

Options:

A.

Welcome and involve the contractors as part of the project team.

B.

Ask the contractors to meet with the customer independently.

C.

Ask the customer to develop a document with the requirements.

D.

Warn and penalize the contractors who do not attend the meeting.

Question 477

During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?

Options:

A.

Assign the work based on the skill sets of team members.

B.

Request feedback from stakeholders about the quality delivery.

C.

Assign the work in consultation with the functional manager.

D.

Discuss this with the team and review the quality process.

Question 478

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?

Options:

A.

Update the communications management plan to satisfy the client's request

B.

Request the client to attend the daily meetings with the project team

C.

Encourage the client to interact with the protect collaboration platform

D.

Ask the product owner to frequently communicate with the stakeholders

Question 479

A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?

Options:

A.

Developed a detailed, phased procurement management plan including all activities required and had the client approve it.

B.

Included the client in all negotiation phases with the consultancy to obtain their advanced approval before signing the contract.

C.

Prepared and negotiated a second contract with the consultancy firm for the remaining 14 months after the first contract signature.

D.

Agreed beforehand with the client on the frequency of reporting on the status of the procurement activities within the project.

Question 480

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

Options:

A.

Inform the relevant stakeholders.

B.

Inform the project team only.

C.

Inform the product owner.

D.

Inform the project sponsor.

Question 481

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Question 482

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

Options:

A.

Create a risk register to track the risks and request additional budget.

B.

Analyze the impact against the release plan if the blocker is not addressed.

C.

Work with the project owner to prioritize the product backlog.

D.

Escalate the situation to the project sponsor for a possible resolution.

Question 483

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.

Add 4 additional weeks to the schedule and request additional resources.

B.

Ask the sponsor to obtain a special work permit to continue work.

C.

Review the project management plan to see the impact of the possible delay.

D.

Crash the resource management plan to keep the schedule on track.

Question 484

During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.

How should the project manager ensure that these changes are managed effectively?

Options:

A.

Include the changes in the backlog and review priorities with the product owner.

B.

Record the changes using the risk register and continue monitoring.

C.

Deny the change requests and keep delivering the project as planned.

D.

Review the project and communications management plan with the main stakeholder.

Question 485

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

Question 486

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

Options:

A.

Log the technical design delay as a risk in the project risk log.

B.

Set up a steering committee session to review the project delay.

C.

Continue with the approved design so that the project is not delayed.

D.

Ask the steering committee to approve a new technical design.

Question 487

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

Options:

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Question 488

While monitoring a project at a work site, the project manager notices that the site team’s work breaks have increased by a few minutes every week. How should the project

manager approach this?

Options:

A.

Reduce payment to the workers due to their extended breaks.

B.

Issue a formal written warning to all hourly workers for their break tardiness.

C.

Have a meeting with the team to discuss the issue and propose solutions.

D.

Dismiss some of the workers for failing to adhere to the break policy.

Question 489

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

Options:

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

Question 490

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project

manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?

Options:

A.

Advise the team member not to share personal information from past projects with the entire team.

B.

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

C.

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

D.

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

Question 491

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

Options:

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

Question 492

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Options:

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Question 493

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)

Options:

A.

Ask human resources (HR) to intervene before it escalates and affects the team's performance.

B.

Arrange individual meetings with the team members who cannot work together effectively.

C.

Address the conflict during team meetings for the entire team to participate and find solutions.

D.

Discuss the conflict early among the affected team members using a direct, collaborative approach.

E.

Plan to resolve the team members' conflicts after the sprint and focus on achieving the goal.

Question 494

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.

Ensure the client representative is involved in the estimation.

B.

Review the completion costs of similar projects.

C.

Ensure that a 20% contingency is included in the estimation.

D.

Review the lessons learned from similar projects.

Question 495

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

Options:

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

Question 496

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.

How should the project manager handle the situation?

Options:

A.

Review validation and control procedures.

B.

Discuss reducing interruptions with the sponsor.

C.

Perform stakeholder requirements activities.

D.

Approach the sponsor about using an agile approach.

Question 497

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.

Lessons learned database

B.

Procurement strategy

C.

Vendor's website

D.

Appropriate financial regulations

Question 498

A company has started developing a new product. During execution the project team notices that another competitor has launched a product with

very similar functionalities and a cheaper market price.

What should have been done differently to avoid this scenario?

Options:

A.

A minimum viable product (MVP) should have been released to get feedback from the market.

B.

More backlog refinement meetings should have been scheduled.

C.

The Kanban method should have been utilized to optimize the work in progress (WIP).

D.

An iterative life cycle approach should have been adopted.

Question 499

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.

Needed to close the work breakdown structure (WBS).

B.

Needed to share it with the stakeholders.

C.

Needed to close out the project or a phase.

D.

Needed to release the team at the end of the project.

Question 500

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?

Options:

A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.

B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.

C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.

Question 501

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

Options:

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

Question 502

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

Options:

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

Question 503

A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?

Options:

A.

Direct the senior-most member to determine the scope on behalf of the team.

B.

Discuss this with the team and decide what the scope of the feature should be.

C.

Ask the team to log the story in the product backlog and move on to the next feature.

D.

Encourage the team to collaborate to resolve their understanding of the feature.

Question 504

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?

Options:

A.

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.

B.

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.

C.

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.

D.

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.

Question 505

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Question 506

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

Options:

A.

Invite the director to attend the daily standup meetings.

B.

Share this with the team and ask them to develop reports for the director.

C.

Introduce the agile aspect to the director and agree on a solution.

D.

Explain to the director that agile projects have live reports.

Question 507

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the

requirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

B.

Accept only those changes to requirements that provide additional value to the project.

C.

Reject all changes that will increase the budget or increase the time line of the project.

D.

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

Question 508

A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed.

What should the project manager do?

Options:

A.

Reopen the quality acceptance documentation to add the sponsor's complaints.

B.

Schedule a quality review meeting and include the sponsor's complaints.

C.

Review best practices and lessons learned and apply them to the project plan.

D.

Postpone the next project phase until the impact of the quality issues is assessed.

Question 509

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for

providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available

in 2 weeks due to some unforeseen problems.

What should the project manager do next?

Options:

A.

Apply the terms and conditions of the contract with penalties.

B.

Issue a change request to reflect the anticipated date for training.

C.

Help the customer find an alternative location to start the training.

D.

Update the project schedule with the new date for training.

Question 510

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team's engagement?

Options:

A.

Collect feedback from the team to discuss alternatives to enhance the communication.

B.

Conduct individual meetings to create a trusting environment with team members.

C.

Establish periodic face-to-face meetings and address the communication topic.

D.

Hold meetings in accordance with the team members’ preferences and availability.

Page: 1 / 170
Total 1702 questions