Pre-Summer Sale- Special Discount Limited Time 65% Offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Exam Practice Test

Page: 1 / 22
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

Options:

A.

Brainstorming

B.

Delphi method

C.

Focus group

D.

Checklist analysis

Question 2

Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simulation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.

Which tool should the risk manager consider for assessing the test risk?

Options:

Question 3

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Question 4

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration.

 

Question 5

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.

4 hours

B.

5 hours

C.

6 hours

D.

12 hours

Question 6

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

Question 7

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis.

 

Question 8

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder's decision regarding the project?

Options:

A.

Perform a risk impact analysis.

B.

Perform a risk reserve analysis.

C.

Perform a procurement analysis.

D.

Perform a stakeholder impact and influence analysis.

Question 9

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

 

Question 10

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Question 11

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project

 

Question 12

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Question 13

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Question 14

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Question 15

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

B.

React to the secondary and residual risks only if they occur.

C.

Include secondary and residual risks as part of the response.

D.

Transfer secondary and residual risks to the project sponsor.

Question 16

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

Question 17

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

Options:

A.

Sensitivity analysis

B.

Simulation analysis

C.

Monte Carlo simulation

D.

Quantitative analysis

Question 18

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Options:

A.

Being able to monitor and control risks throughout the project.

B.

Defining how risk management will be executed throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Question 19

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Question 20

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

Options:

A.

Document the risk in the risk register for analysis.

B.

Document the detailed risk consequences,

C.

Immediately start the contracting process.

D.

Proceed with the quantitative risk analysis.

 

Question 21

The project manager performed' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.

The uncertainty and risk are increasing.

B.

The project schedule is lagging behind.

C.

There is no potential for future deviation.

D.

The project is over budget.

Question 22

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W&S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Question 23

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur.

 

Question 24

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

Question 25

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

Question 26

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Question 27

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

Options:

A.

Quantitative risk analysis

B.

Risk response planning

C.

Monitor and control risks

D.

Risk urgency assessment

Question 28

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

Question 29

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment

 

Question 30

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

 

Question 31

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Question 32

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Question 33

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Question 34

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Options:

A.

Engaging the key stakeholders during the prioritization process

B.

Prioritizing the risks based on the project sponsor's risk appetite

C.

Engaging with the project sponsor before presenting to the board

D.

Working with an established industry standard prioritization method

Question 35

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Question 36

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses

 

Question 37

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners.

 

Question 38

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Question 39

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery.

 

Question 40

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Question 41

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Question 42

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered.

 

Question 43

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Question 44

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.

Import a risk register from other industry chemical laboratories.

B.

Define chemical laboratory safety risk thresholds.

C.

Review published operational experience reports.

D.

Draft threat and opportunity risks that come to mind.

Question 45

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability

 

Question 46

A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.

What should the risk manager advise the team to do first?

Options:

A.

Mitigate the risk by asking the team member to gather more information.

B.

Add the risk to the issue log and revisit it when there is more information.

C.

Arrange a meeting with the stakeholder to discuss the risk and information.

D.

Add the risk to the risk register and gather information about its probability and impact.

 

Question 47

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

 

Question 48

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Question 49

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Question 50

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.

B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.

C.

Conduct a Monte Carlo simulation to understand the probabilities of various risk outcomes.

D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.

E.

Focus attention and resources on identified risks with the highest potential to impact the project.

Question 51

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

Options:

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Question 52

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks.

 

Question 53

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented.

 

Question 54

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Question 55

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simulation

C.

The full risk description

D.

The risk response plan

Question 56

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project's midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Question 57

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Question 58

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Question 59

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.

Contact the risk managers of the other projects and inform them

B.

Include an escalation process in the risk management plan

C.

Take note of the extensive impact of these risks in the risk register

D.

Address the unique characteristics of these risks on a case-by-case basis

Question 60

During project development, a risk manager notices that a major update in the country's regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

Options:

A.

Sensitivity analysis

B.

Threshold analysis

C.

Reserve analysis

D.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

 

Question 61

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response.

 

Question 62

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Options:

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

D.

Hire another developer to support the project, contingent on when the experienced developer returns.

 

Question 63

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart

B.

Ishikawa diagram

C.

Risk breakdown structure (RBS)

D.

Affinity diagram

Question 64

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Page: 1 / 22
Total 221 questions