New Year Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-200 PMI Agile Certified Practitioner (PMI-ACP)® Exam Practice Test

Page: 1 / 15
Total 145 questions

PMI Agile Certified Practitioner (PMI-ACP)® Questions and Answers

Question 1

Project managers use velocity to determine:

Options:

A.

If the team is committing to an appropriate amount of work for the iteration.

B.

How much work each team member is capable of completing during an iteration.

C.

How much work teams that are similar in size are capable of completing during an iteration.

D.

If the Product Owner is prioritizing work appropriately in preparation for iteration planning.

Question 2

Spike solutions are appropriate when:

Options:

A.

the business requirements are vague or inadequate for an iteration.

B.

a technology is understood well and has been used for a while, but needs a problem to be debugged.

C.

there is insufficient time to refactor, but there is a need to resolve a specific problem.

D.

a specific technicalQUESTION NO:needs to be answered, stopping work on the spike as soon as it answers that question.

Question 3

When are acceptance tests typically written for a user story?

Options:

A.

After coding the story, but before user acceptance testing begins

B.

After writing the story, but before coding begins

C.

At the start of Product Backlog prioritization planning

D.

After estimating the Product Backlog, but before Sprint planning begins

Question 4

A common reason that a story may not be estimable is that the:

Options:

A.

team lacks domain knowledge.

B.

business needs are prioritized over the system design.

C.

developers do not understand the tasks related to the story.

D.

team has no experience in estimating.

Question 5

What are the primary outputs of a release planning session?

Options:

A.

Release vision, assumptions, action items, and iteration goals

B.

Prioritized Product Backlog, risks, action items, and release goals

C.

Estimated iteration velocities, risks, action items, and Release Backlog

D.

Risks, action items, dependencies, and Release Backlog

Question 6

Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?

Options:

A.

Fast-Flexible-Flow

B.

Optimize the Whole

C.

Deliver Early and Often

D.

Eliminate Waste

Question 7

During the daily standup meeting, a team member states that an issue has been encountered. This leads to the team members getting into a problem-solving discussion. How should the ScrumMaster respond?

Options:

A.

Ask the team members to table the discussion until after the meeting is over.

B.

If the item is really important, allow the discussion to expedite resolution of the issue.

C.

Abruptly end the daily standup meeting and schedule another meeting to discuss the issue.

D.

Ask the team how they would like to use the daily standup meeting for that day.

Question 8

What key benefits might stakeholders realize from an Agile approach?

Options:

A.

The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily

B.

The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments

C.

Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting

D.

The team’s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments

Question 9

Collaboration can be defined as working together to jointly produce a deliverable or make a decision, whereas coordination is:

Options:

A.

Agreeing on a due date.

B.

Sharing information.

C.

Agreeing on the design.

D.

Pair programming.

Question 10

An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:

Options:

A.

procurement processes by requiring vendors to ship materials as needed.

B.

project cost management by making incremental payments on contracts.

C.

customer satisfaction by specifying project shipping dates in the contract.

D.

project Return on Investment (ROI) by releasing individual features to market.

Question 11

Following chart lists stories for a release of an Agile project;

Question # 11

If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?

Options:

A.

9

B.

10

C.

12

D.

15

Question 12

Which term best describes an Agile project's approach to risk analysis?

Options:

A.

Regression

B.

Pareto

C.

Qualitative

D.

Monte Carlo

Question 13

When moving to Agile project management, a key factor for the project manager’s success will be:

Options:

A.

shifting from a controlling mindset to a facilitating mindset

B.

directing the work in a more incremental fashion

C.

only assigning tasks for the nextiteration

D.

giving up control and rotating management through the team

Question 14

The purpose of a project burndown chart is to:

Options:

A.

Identify and communicate upcoming milestones.

B.

Display the level of effort and resources utilized.

C.

Identify dependencies between sprints or iterations.

D.

Display the remaining work across time.

Question 15

The purpose of the iteration retrospective is to:

Options:

A.

Report progress of the work effort, what work will be done next, and review impediments to progress.

B.

Prioritize the Product Backlog, generate development and testing estimates, and plan the next iteration.

C.

Provide a demonstration of the features developed during the iteration, get feedback from users, and begin testing.

D.

Identify what worked well, what did not work well, and what actions should be taken to improve the process.

Question 16

Which of the following drivers is the most important factor in determining the order in which stories will be developed?

Options:

A.

Relative cost

B.

Customer value

C.

Development effort

D.

Dependencies

Question 17

A ScrumMaster:

Options:

A.

prioritizes the work for each iteration.

B.

directs the activities of the team.

C.

provides leadership, guidance, and coaching.

D.

manages the project scope and budget.

Question 18

Which of the following best represents both a principle of the Agile manifesto and a Lean method of simplicity?

Options:

A.

Maximizing the amount of work not done

B.

Delivering early and continuously

C.

Welcoming changing requirements

D.

Deciding at the last responsible moment

Question 19

How is the participatory design process characterized?

Options:

A.

A well-planned and well-documented process is documented for each of the iterations in the project.

B.

Users including project team members participate in the planning process for the project plan.

C.

End users participate and assist in the design process from the beginning of the project.

D.

A high level brainstorming process is conducted for the project team and the project sponsor.

Question 20

Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

Options:

A.

Split the stories into smaller ones to allow the customer to choose the pieces that they want.

B.

Have the team provide guidance into where their priorities lie to the customer.

C.

Provide additional technical details to give the customer insight into technical challenges.

D.

Have the team rewrite the stories with additional details to clarify requirements.

Question 21

Acceptance tests of user stories are specified by the:

Options:

A.

Customer at the start of the iteration.

B.

Customer as late as possible during the iteration.

C.

Tester after the team has finished the coding.

D.

Development team at the start of the iteration.

Page: 1 / 15
Total 145 questions