A Project Cost Management Plan is created as a part of:
Another term for top down estimating is:.
At which stage, stakeholders have the maximum influence on a project?
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the standard deviation for the estimates?
All are output of verify scope.
The Staffing Management Plan ___________, will be formal or informal.
Control Costs is concerned with:
Which devises and maintains a worktable scheme to accomplish the business need that the project was undertaken to address.
What is the primary purpose of a milestone chart?
What is the purpose of the WBS?
Which is not a technique for Sequence Activities ?
Which of the following documents the characteristics of a product or service that the project was undertaken to build.
What is not among the tools and techniques of an Organizational Planning?
A program is defined in the PMBOK as:
A _______ is a series of actions bringing about a result.
According a PERT weighted average computation, what is the probability of completing the project within plus-or-minus 3 standard deviations of the mean?
What involves determining what quantities are to be used to perform project activities.
The major project scope management process includes:
In which type of organization, a project manager is in complete control of the project?
Activity Resource Requirements is an input to ____________ :
Which of the following is not true for a Resource Leveling:
A Precedence Diagramming Method (PDM) uses which of the following dependencies
What is the lowest level in a work breakdown structure?
Which of the following is true regarding IRR?
As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is:
If BCWP= 450: ACWP= 410, and BCWS= 325, what is the schedule variance and the schedule performance index?
Which of the following illustrate a chart with upper or lower limits on which value of some statistical measure for a series of samples are plotted using sample measure measurement, where the mean and standard deviation are determine from the sample selected?
How many communication channels will be required in a project having five individual participants?
Which characteristic distinguishes the network diagram from the Gant chart?
As a project manager, you are responsible for maintaining and ensuring integrity for all of the following except:
Which statement is not true regarding the issue logs?
The stakeholder's influence is greatest at the ______ of the project.
The process to change a contract clause is _______ the project change control system.
What techniques are used to control the project schedule?
You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?
Which of the following is useful in Identify Risks because it permits a systemic evaluation of the work?
What type of organizational structure usually experiences the MOST team nervousness at project close-out?
Which of the following are not indirect costs?
The project baseline is:
Your upcoming project includes project team members from a foreign country. To make certain that cultural differences do not interfere with team performance, thereby affecting the success of the project, which is your first course of action ?
The level of authority a project manager has is __________.
Planning components are tools or techniques of the Define Activities process. Which of the following are planning components?
Communication between the project manager and the project team members should take place:
Which of the following best describes the risks that still remain after avoidance, transfer, or mitigation responses have been implemented?
Which process involves formal product acceptance and end of a project?
You are project manager of a project and the funding for your project has been reduced. What is the BEST action to take in response to this?
Percent complete is calculated by _________.
How much time does a typical project manager spend communicating both formally and informally?
Risks are accepted when __________.
The most effective method in developing a project team within a matrix organization is to follow the ________.
Technical staffs tend to be particularly responsive to __________.
As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for which of the following:
Which of the following is part of the expectancy theory of motivation?
The major project scope management processes include:
A service or product's reliability and maintenance characteristics are MOST affected by which of the following:
Which of the following is not an input into organizational planning?
Group brainstorming encourages all of the following except ___________.
You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?
Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?
Which of the following is not a process of Project Communications Management?
The party that needs the change resulting from the project, and who will be its custodian on completion is the ___________.
Which of the following is NOT considered as strategy for negative risk ?
Which of the following techniques is used to control the project schedule?
Life cycle costing ________________.
Project initiation is all of the following except:
During the execution phase, a resource is added to the project team. What effect will this have on the project?
In which of the following contract types the seller's profit is limited?
You are the controller on your project. Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?
Which process involves Monitoring, measuring, and taking corrective action?
What-if scenario analysis is done as a part of __________ process.
Reserve analysis is a tool or technique in all of the following processes EXCEPT:
Which of the following is true about procurement documents?
You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?
You are a project manager and now you are in the middle of comparing proposals received from sellers. Comparing proposals received from sellers are done in _________.
During project integration activities, a project sponsor's role can best be described as doing which one of the following?
A contingency plan is ______________.
Which of the following is an example of indirect costs?
Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?
Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?
________ must be measured regularly to identify variance from the plan.
Which of the following are inputs to the Source Selection process?
The sender is responsible for ____________.
AON refers to __________.
How much time does the typical project manager spend communicating both formally and informally?
Formal acceptance by the client or sponsor of the project should be prepared and distributed during which process?
The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called _________.
All of the following aid in achieving consensus EXCEPT _________.
Which of the following is part of the expectancy theory of motivation?
Which of the following contract types places the greatest risk on the seller?
The sending or conveying of information from one place to another is the process of _______________.
Which of the following are NOT outputs of the Activity Duration Estimation process?
Which of the following are the outputs of Collect Requirements Process?
Create Procurement document is done in _______.
The buyer and seller are bound by the ________.
Which process group is for detailed resource assignments and responsibilities?
Stakeholder influence is greatest at the ______ of the project.
Conformance to specifications document is one description of _________.
What is the communication channel delta if the members in the communication plan are increased from 5 to 10?
Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?
_________ is always the lowest risk for the buyer if the scope of work is not well defined.
Administrative Closure should occur ___________.
You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?
You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?
When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?
Which of the following activities is not part of Plan Risk Management?
You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?
Which of the following is NOT an input of close project process?
The main purpose of project initiation is to ________.
Which statement is true about Bottom-up estimating?
During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.
Which of the following plans is not done during the writing of a project plan?
Which document is best suited for tracking the assignment of all resources to specific tasks in a project?