Question 1

Your customer’s initial measurement data (IMD) has been imported and can be viewed through the Measuring Component portal, but is not in the “Final” measurement status.

What can you assume that the IMD has passed?

Options:

A.

Critical Validation

B.

Multiplier Check Validation

C.

Sum Check Validation

D.

CriticalValidation, High/Low Check Validation, and Sum Check Validation

E.

High/Low Check Validation

Question 2

Which option correctly describes the high-level process from loading measurements through calculating usage?

Options:

A.

1.Load Initial Measurements

2. Validate, edit, and estimate Initial Measurements

3. Create Final Measurements

4. Update Initial Measurements

B.

1. Load Initial Measurements

2. Verify, evaluate, and enter Initial Measurements

3. Create Final Measurements

4.Calculate Usage

C.

1. Load Initial Measurements

2. Validate, evaluate, and estimate Initial Measurements

3. Update Initial Measurements

4. Calculate Usage

D.

1. Load Initial Measurements

2. Validate, edit, and estimate Initial Measurements

3. Create FinalMeasurements

4. Calculate Usage

Question 3

When a customer has a specific price for a defined quantity which is different to other customers, where is this specific price for the related Bill Factor defined?

Options:

A.

Bill Factor Characteristic

B.

Bill Factor Value

C.

Service Agreement - Contract Value

D.

Calculation Rule

E.

Account Characteristic

Question 4

Which describes derived values and their relationship with Final Measurements?

Options:

A.

Final Measurementscan have multiple derived values, which represent other values for the same Final Measurement Date/Time.

B.

Derived values can have multiple Final Measurements, which represent other values for the same Initial

Measurement Date/Time.

C.

Final Measurementscan have one derived value, which represents an alternative for the same Final

Measurement Date/Time.

D.

Final Measurements can have one derived value, which represents the Initial Measurement for the same

Final Measurement Date/Time.

Question 5

If a customer makes a payment for more than what is due for the account, which entity contains the logic for how this overpayment should be handled?

Options:

A.

Tender Type

B.

Installation Options

C.

Customer Class

D.

Pay SegmentType

E.

Service Agreement Type

Question 6

Which two plug-in spots can call the rating functionality using base package-supplied algorithm types? (Choose two.)

Options:

A.

Adjustment Type - Adjustment FT Creation

B.

Billable Charge Template

C.

Bill Segment Type - Bill Segment Create

D.

Adjustment Type - Generate

E.

Bill Segment Type - Bill Segment FT Creation

Question 7

Which three statements are true about thedifferent types of measuring components? (Choose three.)

Options:

A.

Seconds-per-interval (SPI) is one of the attributes of scalar measuring components.

B.

Only physical measuring components reference a device configuration.

C.

The terms register and channel are synonyms for measuring component.

D.

The measuring component types are physical, standalone, scratchpad, and TOU.

E.

Scalar measuring components contain a single measurement for an arbitrary period of time.

Question 8

Critical validation rules verify the integrity of the initial measurementdata (IMD). If an implementation needs to

add new critical validations, where would you configure them?

Options:

A.

as new lifecycle algorithms on the IMD Seeder BO (D1-IMDSeeder)

B.

in the pre-processing algorithm of the IMD Seeder BO (Dl-IMDSeeder)

C.

as optionson the IMD Seeder BO (D1-IMDSeeder)

D.

in the schema of the IMD Seeder BO (D1-IMDSeeder)

E.

in the validation algorithm on the IMD Seeder BO (D1-IMDSeeder)

Question 9

At what stage in the initial measurement data (IMD) import process will the application of meter multipliers be performed?

Options:

A.

Critical Validation

B.

VEE

C.

Prepare for VEE

D.

post-VEE

Question 10

Your client has installed scalar devices to measure the solar energy generated (Export) and the energy received (Import) from the National Grid. This data is stored in separate measuring components (registers).

The validation rules are generally the same for both measuring components, but there is one exception. The Negative Consumption check applies only toenergy received (import).

Which two are possible configurations resulting in the Negative Consumption rule being checked for energy received (import) only? (Choose two.)

Options:

A.

Modify the base VEE rule.

B.

Remove the Negative Consumption check from the VEE group.

C.

Create two different VEE groups.

D.

Use Eligibility Criteria.

E.

Use the Skip Flag in the VEE rule.