Summer Sale- Special Discount Limited Time 65% Offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

Microsoft MB-335 Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Exam Practice Test

Page: 1 / 15
Total 152 questions

Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Questions and Answers

Question 1

You need to configure the system to meet the requirements.

What should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 1

Options:

Question 2

You need to set up the chocolate items.

Which values should you select? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 2

Options:

Question 3

You need to configure the system to track the cost and delivery performance of VendorZ.

Which two actions should you perform? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Add an activity to the production route for deliveries.

B.

Create a service product and set Stocked product - Yes.

C.

Add an activity to the production flow for deliveries.

D.

Create a service product and set Stocked product = No.

Question 4

You need to determine the batch values on the combined mix batches for OperatorA.

Which values should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 4

Options:

Question 5

You need to resolve the issue for UserF.

What should you configure? To answer, select the appropriate options in the answer area.

Question # 5

NOTE: Each correct selection is worth one point.

Options:

Question 6

You need to resolve the issue for UserE.

Which configuration options should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 6

Options:

Question 7

You need to resolve the issue for UserB.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Set up configuration and weight for partial visibility.

B.

Create a product master with predefined variants for ounces and boxes.

C.

Set up configuration and weight for full visibility.

D.

Create a catch weight item.

Question 8

You need to resolve the issue for UserG.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 8

Options:

Question 9

You need to configure each item for plastic manufacturing.

Which production types should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 9

Options:

Question 10

You need to configure the system for plastic operations.

Which two parts should be manually reported as finished? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

unmachined plastic pieces

B.

mold tooling

C.

machined plastic pieces

D.

excess plastic

Question 11

You need to set up the correct production solution for the assembly area. Which solution should you implement?

Options:

A.

Standard warehousing with Manufacturing execution

B.

Standard warehousing for all transactions

C.

Advanced warehousing for all transactions

D.

Advanced warehousing with Manufacturing execution

Question 12

You need to configure scheduling for each production area.

Which scheduling options should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 12

Options:

Question 13

You need to configure system attributes.

Which attribute types should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 13

Options:

Question 14

You need to set up the metal production route and BOM.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Set the operation route type as Standard.

B.

Set the input warehouse on the resource to the vendor warehouse.

C.

Set the operation route type as Vendor.

D.

Set all BOM lines warehouse to the production warehouse.

E.

Set all the BOM lines to resource consumption.

Question 15

You need to modify the production order defaults for the manufacturing execution production order Start process.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 15

Options:

Question 16

You need to set up the system to calculate the overhead rates automatically for production.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question # 16

Options:

Question 17

You need to determine the sales price for a new limited-edition bicycle for the summer season.

What should you do?

Options:

A.

Run inventory close for the BOM items for the limited-edition bicycle.

B.

Create the production order for the limited-edition bicycle and click estimate.

C.

Run the category price rules for the limited-edition bicycle using a cost-plus calculation.

D.

Run the pricing simulator for the limited-edition bicycle for a quantity of one.

Question 18

You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question # 18

Options:

Question 19

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.

The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.

You need to resolve the issue.

What should you do?

Options:

A.

Increase positive days.

B.

Decrease positive flays.

C.

Decrease negative days to be less than the item lead time.

D.

Increase negative days to be greater than the item lead time.

Question 20

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP 01 to represent the painting service.

You need to create a subcontracting activity for the painting service.

Solution:

• Create a vendor warehouse for the subcontracting vendor.

• Create a vendor resource and add it to a new work cell for outsource painting.

• Create a production flow transfer activity and specify the vendor warehouse as The target warehouse.

Does the solution meet the goal?

Options:

A.

Yes

B.

No

Question 21

A company uses Dynamics 365 Supply Cham Management.

Several production orders are in the started status.

An issue with equipment causes a rollback in the production status tor some of the orders.

Some orders must be reset once the equipment is repaired, based on which products were being manufactured.

You need to reset the production orders based on the requirements

Which status should you use for each requirement? To answer, drag the appropriate statuses to the correct requirements. Each status may be used once, more than once, or not at all.

You may need to drag the split bar between panes or scroll to view content.

Question # 21

Options:

Question 22

A company produces multiple products that require an installation kit that includes 50 components.

The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOW kit that includes all SO components, but you do not want it to produce a separate production order.

You need to set up the product BOM for the finished good.

What should you do?

Options:

A.

Select Phantom on the engineering fast tab on the kit item.

B.

Change the coverage group on the kit item to Manual.

C.

Change the line type to Pegged supply

D.

Change the line type to Phantom

Question 23

A company uses engineering change management in Dynamics 365 Supply Chain Management. The Product readiness checks feature is turned off.

An existing engineering product must be reconfigured for a new product readiness policy.

You need to change the product readiness policy.

Where should you make this change?

Options:

A.

default order settings

B.

shared product

C.

engineering category

D.

product configuration model

E.

released product

Question 24

A manufacturer uses Dynamics 365 Supply Chain Management.

The engineering department constantly revises product designs to stay current with the latest technology. The customer service department places orders lot the products but frequently adds a prototype product version that is not yet operational.

The manufacturer requites a solution that notifies customer service if a prototype version is selected on a sales order.

You need to configure the solution.

What should you configure?

Options:

A.

engineering product category

B.

version number rule

C.

product lifecycle stales

D.

product release policy

Question 25

You need to configure production operations for the pine and orange scent solutions.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Configure the inventory policy for the item model group to set the value of the Stocked product option to Yes.

B.

Use a purchase agreement as a service agreement.

C.

Allocate subcontracted work in its own cost breakdown block.

D.

Configure a costing resource and requirement to point to a Vendor type resource.

E.

Configure the BOM line to be of type Vendor and associate the corresponding vendor account.

Question 26

You need to plan scheduling for Customer1’s order of unscented solution.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Schedule production based on the availability of raw material.

B.

Split and plan operations in detail for each of the resources.

C.

Schedule productions based on the capacity of the resources.

D.

Run master planning with a specific time fence.

E.

Plan scheduling of the production at the resource group level.

Question 27

You need to configure lot number control for inventory. Which option should you use?

Options:

A.

Physical inventory

B.

Blank receipt allowed

C.

Blank issue allowed

D.

Primary socking

Question 28

You need to configure production control parameters for liquid cleaning solution manufacturing.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Require an electronic signature when the formula is approved.

B.

Select Block editing and approve the formula.

C.

Select the Block removal of approval option for the formula

D.

Select the Block editing option only.

D18912E1457D5D1DDCBD40AB3BF70D5D

Question 29

You need to calculate estimated consumption of ingredients for liquid cleaning solution.

What is the consumption? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 29

Options:

Question 30

You need to resolve the shop supervisor’s issue.

Which options should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 30

Options:

Question 31

You need to resolve the production manager issue.

How should you configure manufacturing execution? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 31

Options:

Question 32

You need to configure the system to meet the order requirements for unscented cleaning solution. Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Configure the ingredient as a restricted and regulated product.

B.

On the inventory management parameters, set the value for the Print Product Safety Data Sheet and Prevent Sales Pack Slip/Invoke Posting to TRUE

C.

Add the ingredients for unscented cleaning solution to a regulated products inclusion list

D.

Ensure that the PSDS file is active and within the expiration date requirements.

E.

In Document Handling, associate the PSDS file with the PSDS record and set restriction field set to Internal

Question 33

You need to configure the reservation methods prototype production order as planned by the engineering team.

How should you configure the prototype production order? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Question # 33

Options:

Question 34

You need to configure the warehouse manager's ModelA subassembly production requirements. Which setting should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 34

Options:

Question 35

You need to resolve the ModelA charging issue.

Which two configurations should you set on the work order finite capacity? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Ignore scheduled execution

B.

Asset

C.

Tool

D.

Worker

E.

Ignore schedule

Question 36

You need to configure the production requirements of the controller.

What should you configure? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Question # 36

Options:

Question 37

You need to resolve the ModelT issue reported by the golf course manager.

Which two features should you configure? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Service subscription

B.

Counter-based maintenance plan lines

C.

Maintenance plan lines for the location

D.

Service type item

E.

Time-based maintenance plan lines

Question 38

You need to configure the production requirements for the QA team. What should you configure?

Options:

A.

product readiness policies

B.

quality order

C.

quarantine order

D.

inventory status

Question 39

You need to configure the two lift kit subassembly cost requirements for production.

Which methods should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 39

Options:

Question 40

You need to configure the solution for the two issues the production manager reported.

How should you complete the configurations? To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Question # 40

Options:

Question 41

You need to create production orders for the new summer limited-edition bicycles.

How should they be created? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 41

Options:

Question 42

You need to report newly manufactured bicycles as finished products.

Which three options can you use? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Route card journal

B.

Standard production order update

C.

Handheld warehouse device

D.

Job card journal

E.

Report as finished journal

Question 43

You need to configure the bicycles’ production resource.

Which option should you use?

Options:

A.

Exclusive capacity set to yes and enter a Batch capacity.

B.

Exclusive capacity set to no and infinite capacity.

C.

Exclusive capacity set to yes and infinite capacity.

D.

Exclusive capacity set to no and enter a Batch capacity.

Question 44

You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Question # 44

Options:

Question 45

You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Question # 45

Options:

Question 46

You need to create the production orders for standard model bicycles.

Which method should you use?

Options:

A.

Sales order line

B.

Master planning execution

C.

Supply schedule form

D.

Released item

E.

All production orders form

Question 47

You need to configure the manufacturing groups for the standard model bicycle and the new limited-edition bicycle for the summer season.

Which object should you use?

Options:

A.

Commerce channels

B.

Operating units

C.

Teams

D.

Legal entities

E.

Departments

Question 48

You need to enable the features and configuration keys for the firepits.

Which two features should you enable? Each answer presents part of the solution.

NOTE: Each correct selection is worth one point

Options:

A.

Engineering attributes

B.

Change management for process manufacturing

C.

Engineering product variants

D.

Engineering change management

E.

Production floor execution management

Page: 1 / 15
Total 152 questions