Weekend Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

ISTQB ATM Advanced Test Management Exam v 3.0 – ISTQB Exam Practice Test

Page: 1 / 5
Total 50 questions

Advanced Test Management Exam v 3.0 – ISTQB Questions and Answers

Question 1

You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

Options:

A.

Wideband defphi

B.

Planning poker

C.

Three-point estimation

D.

Extrapolation

Question 2

In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''

Options:

A.

Never

B.

If the defect can be fixed in the same iteration in which it was found

C.

the defect can be fixed in a later hardening sprint

D.

If the defect must be fixed by another team

Question 3

Your team has been assigned to test a loyalty card programfor a supermarket chain.Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics

Given only this information what test approach would be most appropriate?

Options:

A.

Model-based

B.

Experience-based

C.

Risk-based

D.

Requirements-based

Question 4

Which of the following best describes the appraisal costs in the cost of quality'

Options:

A.

The cost spent preventing defects from occurring in the first place

B.

The cost for performing dynamic testing

C.

The cost for fixing defects

D.

The cost for lawyers to deal with a lawsuit over a defect

Question 5

At what testing level do the test management activities Include coordinating with end users7

Options:

A.

Component testing

B.

Component Integration testing

C.

System testing

D.

Acceptance testing

Question 6

Which test process improvement model consists of five maturity levels?

Options:

A.

TMMi®

B.

TPI® NEXT

C.

GQM

D.

CMMi®

Question 7

Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?

Options:

A.

Defects that are projected but have not been found yet

B.

Defects fixed but not yet closed

C.

Defects that have resulted from regressions

D.

Defects that will be introduced to production

Question 8

You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:

Question # 8

Given this information what is a critical metric you are missing?

Options:

A.

Number of tests passed

B.

Number of defects outstanding

C.

Residual risk

D.

Planned vs actual cost of testing

Question 9

There is a debate in your organization about who can close a defect report The developers think theyshould be able to reject and close defects without any further steps The testers are not happy with this approach as they are afraid the rejections may go undetected and the developers may close something without understanding the real problem

How can this problem be rectified7

Options:

A.

Only testers should be allowed to close defect reports

B.

Only management should be allowed to close defect reports

C.

No one should close a defect report until the release is completed and the product is successfully deployed to production

D.

Closure should only occur when a defect is fixed and tested

Question 10

If you are monitoring code coverage during testing to determine what areas still need testing what type of testing is likely occurring?

Options:

A.

Black-box

B.

White-box

C.

Functional

D.

Non-functional

Question 11

You are managing the testing for a bank card project.The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lotof risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving

You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?

Options:

A.

Automate the testing of the untested elements to ensure they are covered

B.

Block the go-live and start testing the low-risk elements immediately

C.

Transfer the risk of the untested low-risk items to the help desk

D.

Select one of the low-risk elements and perform depth testing to assess the residual risk

Question 12

Which ofthe following Is the common setof information to be produced in a test estimate''

Options:

A.

Number of people number of systems lines of code, cost

B.

Time per person budget end date start date

C.

Test effort test duration time to complete, cost

D.

Effort time cost, test activities

Question 13

You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision table and then collapse that table You will then assess the results For this assessment, whatcompetencies are you validating?

Options:

A.

Professional and methodical

B.

Social and personal

C.

Professional and social

D.

Methodical and personal

Question 14

You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?

Options:

A.

Social

B.

Professional

C.

Methodological

D.

Biological

Question 15

You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?

Options:

A.

Reassess the risk with a higher likelihood number

B.

Reassess the risk with a higher impact number

C.

Concentrate more testing in the area because the risk is clearly higher

D.

Concentrate less testing in the area because the defects are already found

Page: 1 / 5
Total 50 questions