Halloween Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

Exin CDCS EXIN EPI Certified Data Centre Specialist Exam Practice Test

Page: 1 / 6
Total 60 questions

EXIN EPI Certified Data Centre Specialist Questions and Answers

Question 1

When shielding material reaches its saturation point, what will be the impact?

Options:

A.

The shielding material will reach its optimal shielding performance state.

B.

The shielding material will no longer be able to attenuate (reduce) additional EMF.

C.

The shielding material will increase its permeability factor.

D.

The shielding material will reach its maximum electrically charged state.

Question 2

What should be considered when installing overhead data cabling?

Options:

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

Question 3

When are the wet bulb and dry bulb temperatures identical?

Options:

A.

When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAE

B.

When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAE

C.

When the relative humidity is at the best practice value for relative humidity, being 50% RH

D.

When the relative humidity is 100%

Question 4

The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.

Is this acceptable?

Options:

A.

Yes, this is allowed according to the standards and guidelines

B.

As long as it does not exceed the average server room temperature of 38 °C/100 °F

C.

Depends on the ANSI/TIA-942 Rating the data center needs to comply with

D.

No, the temperature needs to be 20 °C/68 °F

Question 5

The temperature in the computer room is being increased from 18°C/64°F to 27°C/81°F.

What is the impact, if any, on the amount of gas required to suppress a fire assuming the gas is a Halocarbon?

Options:

A.

The amount of gas required will be higher

B.

The amount of gas required will not change

C.

The amount of gas required will be lower

D.

The change to the amount of gas cannot be determined without knowing the change in humidity as well

Question 6

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

Options:

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Question 7

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

Options:

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Question 8

You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

Options:

A.

12 Amperes

B.

30 Amperes

C.

60 Amperes

D.

80 Amperes

Question 9

What mainly affects the cooling capacity of a raised floor tile?

Options:

A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

Question 10

You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.

What should you recommend?

Options:

A.

Review the cable lengths of each UPS to the common busbar

B.

Nothing, there is no reason for any concern

C.

Review the common mode noise levels within the computer room

D.

Review the harmonics levels within the computer room

Question 11

Which formula is correct?

Options:

A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

Question 12

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

Options:

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

Question 13

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?

Options:

A.

It can only be used in computer rooms which have sufficient air changes per hour.

B.

The gas containers need to be close to the hazard area.

C.

It can only be used in non-continuous occupied areas.

D.

It can only be used in computer rooms where you have sufficient positive pressure.

Question 14

You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?

Options:

A.

No, there is a significant difference in the formula for the different types of fire suppression gases.

B.

Yes, as long as you take the difference between the net and gross volume into account.

C.

Yes, as long as you use the same units of measure, i.e., kg/m³ or lbs/ft³.

D.

Yes, as long as you change the 'S' factor of the formula to reflect the gas type used.

Question 15

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

Options:

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

Question 16

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?

Options:

A.

UPS efficiency

B.

Inverter efficiency

C.

Load imbalance on the phases

D.

Available battery charging current

Question 17

From the options indicated, what is the correct starting point for the raised floor installation?

Question # 17

Options:

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Question 18

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

Options:

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators willrun all the time

Page: 1 / 6
Total 60 questions