When shielding material reaches its saturation point, what will be the impact?
What should be considered when installing overhead data cabling?
When are the wet bulb and dry bulb temperatures identical?
The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.
Is this acceptable?
The temperature in the computer room is being increased from 18°C/64°F to 27°C/81°F.
What is the impact, if any, on the amount of gas required to suppress a fire assuming the gas is a Halocarbon?
The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).
What influence does this have on Electrostatic Discharge (ESD)?
When designing a data center network, your company wants to minimize the number of network switches to manage.
What type of physical cabling layout would be the best choice?
You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.
What mainly affects the cooling capacity of a raised floor tile?
You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.
What should you recommend?
Which formula is correct?
In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?
What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?
You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?
A data center has its own power supply from the public utility and receives chilled water supply from the building owner.
What needs to be taken into consideration when calculating the PUE?
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
•Rated power: 30 kVA
•Rectifier input voltage: 400 V/3 phase
•Rectifier input power factor: 0.8
•Battery rated voltage: 384 V
•Number of cells: 192
•End of discharge voltage: 308 V
•Inverter output voltage: 400 V/3 phase
•Inverter output power factor: 0.8
What information is missing to perform the battery calculation?
From the options indicated, what is the correct starting point for the raised floor installation?
A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.
What type of generators should be installed?