EMC D-PEXE-IN-A-00 Dell PowerEdge XE9680 and XE8640 Install Exam Practice Test

Page: 1 / 1
Total 14 questions

Dell PowerEdge XE9680 and XE8640 Install Questions and Answers

Question 1

A deployment engineer is connecting the network cables on an XE9680 server. The data center administrator wants to know why the server does not have an OCP card for network connectivity.

How should the engineer respond to the administrator's query?

Options:

A.

An OCP card is required for the server to achieve POST when powered on.

B.

The LOM card acts as an OCP card and supports OCP 3.0.

C.

The OCP card is an optional component.

D.

The server does not support an OCP card.

Question 2

A deployment engineer is installing a PowerEdge XE8640 server. The rack has four PDUs. Looking at the rear of the rack, one power source provides power to the two left PDUs. A different power

source provides power to the two right PDUs.

What side of the rack should XE8640 PSU 1 and PSU 2 be connected?

Options:

A.

PSU 2 in the left and PSU 1 in the right

B.

PSU 1 and PSU 2 in the left PDUs

C.

PSU 1 and PSU 2 in the right PDUs

D.

PSU 1 in the left and PSU 2 in the right

Question 3

A deployment engineer is installing eight PowerEdge XE9680 servers. Two servers will be installed in each of four racks. The data center managers must plan for the power needed to supply power to

the four racks.

What power consumption information can the deployment engineer give the data center manager?

Options:

A.

Each rack must have at least 6 PDUs for power high availability.

B.

Each server has four 2800-Watt, 15.6 Amp PSUs.

C.

Each rack must power 12, 2800-Watt, 15.6 Amp PSUs.

D.

Each PDU must use a C20-type connection.

Question 4

A deployment engineer is preparing to install three PowerEdge XE9680 servers in a rack supplied by the customer.

What must they before going on-site to install the servers?

Options:

A.

The rack can accommodate the length of the servers.

B.

The customer completed the required training on the server.

C.

The rack will have a top-of-rack switch.

D.

The rack has at least six PDUs and two power sources.

Page: 1 / 1
Total 14 questions