Summer Sale- Special Discount Limited Time 65% Offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

Certinia AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Exam Practice Test

Page: 1 / 8
Total 78 questions

Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Question 1

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Question 2

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Question # 2

Options:

Question 3

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

Options:

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Question 4

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Question 5

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company's revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Question 6

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Question 7

An external web developer is to be contracted to create the new coffee bar

insurance area on the existing web site. The chosen web developer will only

agree to work on a 'fixed price for a fixed specification' contract.

What action should the Project Manager take?

Options:

A.

Ensure the later elements of the project reflect the most valuable features

of the product being built by the contractor.

B.

Agree to a 'fixed price for a fixed specification' contract with a requirement

for the web developer to provide daily progress reports.

C.

Refuse to employ the chosen web developer as this is not an Agile

approach to project management.

D.

Divide the work into component parts to ensure the web developer is

focused on, and is paid to deliver, only what is specified for each

component.

Question 8

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Question 9

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director's requirements in detail but leave the

input of others until later in the project.

Question 10

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Question 11

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

Options:

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

Question 12

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Question # 12

Options:

Question 13

Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?

Options:

A.

Details of which areas will require seeding in order to become lawn, and which are to become planted borders, should be captured.

B.

The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.

C.

The scope of the project should be agreed before moving into the Foundations phase.

D.

The responsibility for setting the priority of each of the requirements identified should be assigned to the Project Manager.

E.

Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.

Question 14

How should the Project Manager assist the plumbers to deliver the plumbing?

Options:

A.

Split the entire Solution Development Team into smaller teams covering specific locations of the house.

B.

Decide on the location of the radiators on behalf of Architecture Angels.

C.

Establish an inter-team competition to see which team can complete first.

D.

Approve each Timebox before work continues in the next.

Question 15

Answer the following questions about the tracking and control activities carried out within the project.

Decide whether each activity has been applied appropriately and select the response that supports your decision.

During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager

organized a Facilitated Workshop with the project team to discuss and agree the requirements.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.

B.

Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.

C.

No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.

D.

No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders'

expectations.

Question 16

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Question 17

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Question 18

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company's

bank. These scripts will be used

to test the link from the

company's website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website's

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

Question # 18

Options:

Question 19

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Collaborate.

D.

Never compromise quality.

Question 20

Which 2 individuals would be suitable for the role of Workshop Facilitator?

Options:

A.

Team Leader

B.

IT Operations Manager

C.

Marketing Director

D.

Software Developer

E.

Project Manager

Question 21

Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the

project in the Prioritised Requirements List?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Project Manager and Solution Development Team.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Question 22

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox's deliverable as a whole, in order to keep focus on the business need.

B.

Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.

C.

No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements' acceptance criteria, with nothing extra.

D.

No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.

Question 23

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Page: 1 / 8
Total 78 questions