Halloween Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

Adobe AD0-E903 Adobe Workfront Project Manager Professional Exam Practice Test

Page: 1 / 7
Total 70 questions

Adobe Workfront Project Manager Professional Questions and Answers

Question 1

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month."

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select "month of year."

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month of year."

Question 2

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

Options:

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

Question 3

What are two ways to associate milestone steps to tasks? (Choose two.)

Options:

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Question 4

Which two statements are true about Groups and Teams? (Choose two.)

Options:

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Question 5

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Question 6

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Options:

A.

The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.

B.

Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.

C.

The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Question 7

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Question 8

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics

B.

Risks, planned hours, and resource utilization

C.

Project status, Updates, and Sharing

Question 9

The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.

Which task settings need to be configured to meet these requirements?

Options:

A.

The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.

B.

The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

C.

The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

Question 10

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

Options:

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.

Question 11

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

Options:

A.

A user that has access to a burndown

B.

A job role labeled as Agile User

C.

A team marked as an agile team

Question 12

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

Question 13

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Question 14

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

Options:

A.

Estimated Date

B.

Projected Date

C.

Planned Date

Question 15

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

Options:

A.

TODAY + 1bm

B.

TODAY + 1m

C.

CURRENTDATE + 4w

Question 16

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

Options:

A.

Utilization

B.

Workload Balancer

C.

Hours

Question 17

Question # 17

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Question 18

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

Options:

A.

Email, Workfront Home, Project tasks list

B.

Email, Automatic Reminders, Workfront Home

C.

Event Notifications, Approval processes, Email

Question 19

What occurs when an individual enters a new commit date that is after the original planned date of a task?

Options:

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Question 20

When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?

Options:

A.

Add a custom form

B.

Attach a template to the project

C.

Add tasks

Question 21

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

Options:

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Page: 1 / 7
Total 70 questions