APMG-International AgilePM-Foundation Agile Project Management (AgilePM v3) Foundation Exam v3 update Exam Practice Test

Page: 1 / 15
Total 150 questions

Agile Project Management (AgilePM v3) Foundation Exam v3 update Questions and Answers

Question 1

According to Tuckman, in what stage of the team development model can everyone move on to new things, feeling good about what has been achieved?

Options:

A.

Forming.

B.

Storming.

C.

Performing.

D.

Adjourning.

Question 2

Which is a factor used in the 'change formula' (Beckhard and Harris)?

Options:

A.

Level of dissatisfaction with the status quo.

B.

Expected return on investment and benefits.

C.

The quality of the leadership.

D.

Elapsed time it will take to achieve the change.

Question 3

What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

Options:

A.

Business Visionary

B.

Technical Coordinator

C.

Business Analyst

D.

Team Leader

Question 4

Which of the following statements about data analytics are true?

    The more data you have, the better the results.

    Obtaining new data from external sources is beneficial and removes bias.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 5

According to Pink, which three factors are key motivators for 'knowledge work'?

Options:

A.

Dissatisfiers, rewards, and safety.

B.

Autonomy, safety, and self-esteem.

C.

Hygiene factors, autonomy, and self-actualization.

D.

Autonomy, mastery, and purpose.

Question 6

Which purpose relates to the Consolidation in a structured Timebox?

Options:

A.

To confirm the detail of all the requirements to be delivered by the structured Timebox.

B.

To address the requirements and test the structure Timebox product.

C.

To formality accept the structured Timebox deliverables.

D.

To tie up any loose ends related to Evolutionary Development

Question 7

Where information is constantly changing, which of the following would typically be the least effective way to communicate it?

Options:

A.

Video conference

B.

Written document

C.

Teleconference

D.

Email

Question 8

How does DSDM differ from most other Agile approaches?

Options:

A.

It focuses on the entire project lifecycle

B.

It focuses on the development of products

C.

It focuses on the delivery of products

D.

It focuses on the collaborative working of teams

Question 9

Which of the following statements are true?

    The 'change curve' describes a normal human reaction to change.

    The 'change curve' only applies to changes that are perceived as negative.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 10

Why do Line Leaders make effective Change Agents?

Options:

A.

They have local decision-making authority.

B.

As leaders, they are unaffected by the change.

C.

They can support and influence local staff.

D.

They have the time to dedicate to the change.

Question 11

In a free format Timebox, when should reviews take place?

Options:

A.

During the Kick-Off phase

B.

Throughout the body of the Timebox.

C.

During the Close.Out phase

D.

After the Timebox has been completed

Question 12

What kind of power is conveyed by a manager who is admired and respected by their subordinates and seen as a role model?

Options:

A.

Legitimate.

B.

Reward.

C.

Coercive.

D.

Referent.

Question 13

Which of the following statements about a communication plan are true?

    Same overall format for all change initiatives.

    Content will differ depending on the scale and complexity of change.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 14

An organization has decided to roll out the transition to a new software application, one department at a time. What type of delivery strategy is being adopted?

Options:

A.

Big Bang.

B.

Phased.

C.

Voluntary Adoption.

D.

Many small incremental/iterative releases.

Question 15

How does the Project Approach Questionnaire (PAQ) help in identifying and managing approach-based risks?

Options:

A.

By highlighting areas where the project’s culture, leadership, or governance may not align with AgilePM principles.

B.

By ensuring that all project team members agree with the AgilePM approach, thereby eliminating the need…

C.

By providing a one-time assessment at the project’s conclusion to identify risks retrospectively.

D.

By solely focusing on technical risks, ignoring cultural and leadership aspects.

Question 16

Which of the following is a DSMD principle?

Options:

A.

Build incrementally from firm foundations

B.

Build incrementally from Feasibility onwards

C.

Build incrementally in Timeboxes

D.

Build incrementally

Question 17

What defines how well, or to what level a solution needs to perform?

Options:

A.

Functional Requirements

B.

Non-Functional Requirements

C.

Testable Requirements

D.

Tangible Requirements

Question 18

Who is responsible for the application of Principle 8, Demonstrate Control?

Options:

A.

Collectively applied by the whole team

B.

The project-level roles

C.

Team Leader

D.

Project Manager

Question 19

During what phase should a baseline of the Evolving Solution be put into operational use?

Options:

A.

Foundations

B.

Evolutionary Development

C.

Deployment

D.

Post-Project

Question 20

In what phase is it first established whether further investigation of the project is justified?

Options:

A.

Pre-Project

B.

Feasibility

C.

Foundations

D.

Evolutionary Development

Question 21

Which competence is NOT required within the Solution Development team?

Options:

A.

All members to be multi-skilled experts

B.

Business knowledge

C.

Technical expertise

D.

Willingness to work with other

Question 22

Which of the following statements about Scrum Theory is true?

    Scrum employs an iterative approach (correcting the typo “interactive” to “iterative” as requested)

    Decisions should be based on evidence

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Question 23

What event can be added to the structure of a Sprint to help facilitate cross-team planning?

Options:

A.

Project Sprint Planning

B.

Project planning event

C.

Sprint Planning

D.

Sprint Retrospective

Question 24

Identify the missing words in the following sentence.

Principles 1 –Focus on the Business Need suggests that every decision taken during a project should be [?] – to deliver what the business needs to be delivered.

Options:

A.

The responsibility of the Business Sponsor

B.

Share between all of the project roles

C.

Viewed in light of the overriding project goal

D.

Made collaboratively

Question 25

Which of the following statements, about the use of symbolic actions and symbolism to appeal to people’s hearts and minds, are true?

    Leaders must lead by example.

    Only leaders can influence change.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 26

What is the purpose of documenting the 'Measurement methodology' in a change communication strategy?

Options:

A.

Assess the effectiveness of the communication efforts.

B.

Communicate test activities for the final solution.

C.

Quantify the number of people impacted by the change.

D.

Ensure everyone understands the value of the change.

Question 27

Which of the following is an AgilePM principle?

Options:

A.

Never compromise your integrity

B.

Never compromise quality

C.

Never compromise the team

D.

Never promise quality

Question 28

In which of the project variables does AgilePM recommend placing contingency?

Options:

A.

Time

B.

Cost

C.

Quality

D.

Features

Question 29

If two separate development teams are required to work on the same project, how will this be managed?

Options:

A.

Both teams can share the same Product Owner

B.

Each team will need a different Scrum Master

C.

Each team will have a different Business Visionary

D.

There will be two projects with different project roles

Question 30

Which of the following helps to build competence in collaboration?

    Rewarding individual efforts

    No blame culture

    Asking for help

    Setting clear goals

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 31

According to the 'change formula' (Beckhard and Harris), which response will increase the desirability to an individual of the proposed change or end state?

Options:

A.

Focus on the benefits of the change.

B.

Communicate the 'burning platform.'

C.

Clarify the steps users need to take.

D.

Put mitigations in place to reduce risk.

Question 32

Which information is given in the Solution Architecture Definition?

Options:

A.

A high-level design framework for the solution.

B.

A snapshot of the evolving business, solution and management products

C.

The tools and standards to be used in Evolutionary Development

D.

The strategy for testing

Question 33

In the context of AgilePM, what two types of Increment are associated with what is delivered?

Options:

A.

Solution and Product

B.

Timebound and Freeform

C.

Product and Process

D.

Team and Individual

Question 34

Which of the following roles may be substituted for a Scrum Master?

Options:

A.

Team Leader

B.

Project Manager

C.

Product Owner

D.

Developer

Question 35

Which of the following statements, about building and maintaining engagement throughout change, are true?

    Engaging people in change is simple and routine.

    A simple formula can be applied for all change situations.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 36

Which of the following reasons support why Agility in project management is always advantageous?

    Assumptions are often flawed

    Flexibility enables competitive advantage

    Uncertainty leads to reduced ambiguity

    Deferring decisions is advantageous

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 37

Which of the following statements, about the behavior of effective change managers as agile practitioners, are true?

    They should take a single framework and apply it persistently.

    They should remain resilient, flexible, and willing to learn.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 38

Considering the words of the Agile Manifesto, which of the following is true?

Options:

A.

Contractual agreements should be avoided if possible

B.

Contractual agreements should be encouraged by default

C.

Contractual agreements should be considered for their value

D.

Contractual agreements must be standardized for simplicity

Question 39

The Product Owner has identified the need for staff training, to ensure the value from the evolving product is fully realized.

Which role should the Product Owner discuss this with?

Options:

A.

Business Visionary

B.

Business Sponsor

C.

Project Manager

D.

Scrum Master

Question 40

In which of the following circumstances should processes and tools be prioritized over individuals and interactions?

Options:

A.

Need to demonstrate formal control over processes

B.

Requirement to create and approve documentation

C.

Contractual obligations

D.

None of the above

Question 41

What role is responsible for the delivery of the project from Foundations through to Deployment?

Options:

A.

Business Sponsor

B.

Business Visionary

C.

Project manager

D.

Technical Coordinator

Question 42

Which of the following statements is true?

Options:

A.

Project management is concerned with a wider context than product development.

B.

Project management addresses more complex problems than product development.

C.

Product development focuses primarily on who is involved and why it should be.

D.

Product development focuses on governance of the environment.

Question 43

Which of the following is NOT a Project role?

Options:

A.

Business Visionary

B.

Solution Architect

C.

Project Manager

D.

Solution Developer

Question 44

Both numerical and subjective methods can build a picture of how effective your change interventions are. Which type of measure can help us to understand why, how, or what happened behind certain behaviors?

Options:

A.

Qualitative.

B.

Quantitative.

C.

Leading.

D.

Lagging.

Question 45

In combination with Scrum, what does AgilePM provide for Scrum Masters?

Options:

A.

An opportunity to serve the organization by leading, training, and coaching the organization in its Scrum adoption

B.

A set of practices, tools, techniques, and methods to enhance the use of Scrum

C.

A framework that helps teams generate value through adaptive solutions for complex problems

D.

An incremental and evolutionary approach to product development that evolves with time

Page: 1 / 15