New Year Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

AACE International CCP Certified Cost Professional (CCP) Exam Exam Practice Test

Page: 1 / 19
Total 189 questions

Certified Cost Professional (CCP) Exam Questions and Answers

Question 1

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 1

The amount of interest paid during the fifth year of depreciation would be:

Options:

A.

$126.00

B.

$1,200.00

C.

$1,260.00

D.

$12,000.00

Question 2

Question # 2

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?

Options:

A.

0.96

B.

0.88

C.

0.84

D.

1.14

Question 3

The written word is often more useful than the spoken. Guidelines for writing include:

Options:

A.

Use short sentences; use short words; avoid jargon and abbreviations; use complete sentences; stick to one idea per paragraph; have a beginning, middle and end; be accurate

B.

Organize the background information; state the problem list the options or alternatives; state the recommendation (s); conclude and summarize with why the recommendation is the best way to proceed

C.

Follow an outline; allow some time for "cooling" after compiling the draft before revising; when revising, allow plenty of time for several sessions

D.

Explain, report, describe, clarify, define and demonstrate

Question 4

What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?

Options:

A.

WBS element

B.

Activity

C.

Resource

D.

Commodity

Question 5

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

Options:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Question 6

A work breakdown structure (WBS) is developed because:

Options:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Question 7

Which of the lol owing comparisons is commonly used in forensics schedule analysis (FSA)?

Options:

A.

Cost performance index (CPI) to schedule performance index (SPI)

B.

Forensic productivity analysis

C.

Earned value vs scheduled value

D.

As-planned vs as-built

Question 8

In the application of the benefit/cost method of analysis, what are the criteria for determining whether a proposed project is acceptable?

Options:

A.

B/C is - 1.0

B.

B/C is <1.0

C.

B/C is > minimum ROR

D.

B/C is >1.0

Question 9

Question # 9

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

Options:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above

B.

Bid unit rate, owner quantities are within estimate range

C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range

D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range

Question 10

When the project plan is implemented:

Options:

A.

Activities are carefully monitored and controlled against the baseline

B.

The basis for payment applications is formalized

C.

The forward and backward pass is identified

D.

CPI and SPI can be calculated and reported

Question 11

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following is least likely to improve a large earthmoving contractor's productivity?

Options:

A.

Using apprentice operators to save labor costs

B.

Starting summer work in the early morning hours to minimize work during peak heat periods of the day

C.

Remove underground hazards prior to excavation work

D.

Replacing old excavators with new, larger excavators

Question 12

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

Options:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Question 13

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The taxable income in year number 5 is:

Options:

A.

$17,543

B.

$121,551

C.

$42,543

D.

$125,00

Question 14

Question # 14

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

Options:

A.

Engineer/contractor working for the owner (Plan B)

B.

Subcontractor working for contractor (Plan A or B)

C.

Contractor working directly for engineer (plan A or B)

D.

Engineer working for the owner (Plan A)

Question 15

Question # 15

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, copper prices will have increased by what percentage over today's price?

Options:

A.

4.6%

B.

3.5%

C.

6.6%

D.

2.5%

Question 16

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:

A.

$60,000

B.

$41,250

C.

$33,000

Question 17

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow’s hierarchy of needs?

Options:

A.

Belonging needs

B.

Self-actualization

C.

Knowledge

D.

Pay and compensation

Question 18

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

Options:

A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

Question 19

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

Options:

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Question 20

Which of the following is a disadvantage to using target contract as a method of contracting?

Options:

A.

Encourages economic and speedy completion

B.

No opportunity to competitively bid the targets

C.

Almost immediate start on the work, even without scope definition

D.

Flexibility in controlling the work

Question 21

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

Options:

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Question 22

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

A cyclical process model was chosen as the basis for total cost management (TCM) because:

Options:

A.

It is one of the basic tenets of quality improvement

B.

Refinement is needed to prepare the estimate at completion (EAC)

C.

Strategic assets and projects have inherent life cycles

D.

It facilitates development of budgets and schedules

Question 23

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Activity total slack

B.

Remaining duration

C.

Just-in-time" scheduling

D.

Free float

Question 24

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

Options:

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Question 25

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 25

The equivalent value of an investment alternative in today's dollars is referred to as the:

Options:

A.

Break-even point

B.

Rate of return

C.

Net present worm

D.

Future value

Question 26

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?

Options:

A.

Schedule is good, cost is bad

B.

Schedule is good cost is good

C.

Schedule is bad cost is good

D.

Schedule is bad, cost is bad

Question 27

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Total float

B.

Remaining duration

C.

Free float

D.

Just-in-time scheduling

Question 28

Which of the following is NOT a part of the five (5) phases of value engineering?

Options:

A.

Cost reduction

B.

Functional analysis

C.

Creative

D.

Information gathering

Question 29

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?

Options:

A.

Start to start

B.

Star to finish

C.

Finish to start

D.

Finish to finish

Question 30

Budgeted cost of work scheduled is all of the following except:

Options:

A.

Total costs incurred in accomplishing work in a given-time period

B.

Baseline for performance measurement

C.

Sum of the budgets for work scheduled

D.

Includes portion of the budget for level-of-effort work

Question 31

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the "book value (BV) of the asset at the end of 5 years?

Options:

A.

$64,000

B.

$16,000

C.

$3,200

D.

$60,000

Question 32

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

Options:

A.

Liability insurance

B.

Performance bond

C.

Bid bond

D.

Surety bond

Question 33

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of SO 45 cents is estimated.

The monthly fixed costs are: Rant-$1,600

Wages - S4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:

A.

$33,750

B.

$375,00

C.

$7,500

Question 34

Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.

Question # 34

What is the late finish date of activity 50?

Options:

A.

Day 47

B.

Day 38

C.

Day 28

D.

Day 37

Question 35

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.

Options:

A.

Need satisfaction

B.

Belonging needs

C.

Self-actualizations

D.

Esteem

Question 36

Question # 36

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Calculate the mean unit cost.

Options:

A.

$48.09

B.

$48.22

C.

$48.35

D.

$46.59

Question 37

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following statements is correct?

Options:

A.

The graph of a normal curve is bell-shaped and is symmetrical about the standard deviation.

B.

The graph of a normal curve is bell-shaped and is symmetrical about the variance.

C.

Some graphic methods for describing quantitative data ate histograms and frequency distribution.

D.

Some graphic methods for describing qualitative data are histograms and frequency distribution.

Question 38

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The compound interest factor used to determine Present Value in year number 5 is:

Options:

A.

0.3790

B.

0.6209

C.

1.6051

D.

0.6830

Question 39

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today?

Options:

A.

$3,855

B.

$8,129

C.

$6,209

D.

$3,791

Question 40

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Fred Fiedler's contingency model suggests that:

Options:

A.

Leadership styles are just the opposite of the managerial grid model

B.

Successful leadership depends upon a good match

C.

between the style of the leader and the demands of the situation

D.

Successful leadership can always be imposed by experienced supervision

E.

A relationship oriented leader described the least preferred worker in an unfavorable light

Question 41

What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

Options:

A.

Engineer

B.

Alternate

C.

Project Manager

D.

Agent

Question 42

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

SCENARIO: A can manufacturing company requested you to provide data for their decision making. The unit prices of the can vary but an average selling price of $0.55 cents and average cost of $0.45 cents is estimated.

The monthly fixed costs are:

Rent-SI .600

Wages - $4.000

Miscellaneous fixed expenses - $500

Marketing team observed that factory can safely increase their unit selling price to S0.60 cents. The new break even units for the sales based on new contribution margin will be:

Options:

A.

20,000 units

B.

60,000 units

C.

6,000 units

D.

40,000 units

Question 43

An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.

The villa could be recommended for purchase at all of the below-mentioned prices except:

Options:

A.

$94,500

B.

$92.800

C.

$90,5000

D.

$93,500

Question 44

The goal of listening is to:

Options:

A.

Analyze what the speaker is saying

B.

Find out what is going on

C.

Have time to formulate your thoughts on the subject

D.

Improve communication

Question 45

Question # 45

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.

45%

B.

50%

C.

95%

D.

30%

Question 46

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

Question # 46

What is the median unit cost?

Options:

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Question 47

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is a method for figuring estimate at completion (EAC)?

Options:

A.

BCWP + (BAG - ACWP)

B.

ACWP + (BAC - BCWS)

C.

BCWS + (BAG -ACWP)

D.

ACWP + (BAC - BCWP)

Question 48

How can the quality of a cost/capacity factor estimate be improved?

Options:

A.

Validate the capacity factor from similar, recently completed projects

B.

Validate law productivity from recently completed projects

C.

Verify the labor rates used in the estimate

D.

Verify the equipment costs used in the estimate

Question 49

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

Options:

A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

Question 50

In order to withdraw $400 at the end of each year for seven years, what amount should be deposited at 6.0% interest to leave nothing in the fund at the end of seven years?

Options:

A.

$2,233

B.

$3,357

C.

$2,483

D.

$2,968

Question 51

______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.

Options:

A.

Economic optimization

B.

Simulation

C.

Linear programming

D.

Dynamic programming

Question 52

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

Options:

A.

To be exactly the percentages stated

B.

To fall within the percentage range stated

C.

To be higher or lower that the percentages stated

D.

To be outside the percentages stated

Question 53

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

Options:

A.

Ratio/level of effort

B.

Start/finish

C.

Units completed

D.

Incremental milestone

Question 54

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 54

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

Options:

A.

$11,499.00

B.

$4,124.00

C.

$9,876.00

D.

$10,765.00

Question 55

Money is value Having money when you need it is very important Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also. planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically, there is the single payment mothed that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capita1 recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.

Which of the following is not one of the requirements to form a contract?

Options:

A.

Consideration

B.

Competent parties

C.

Legality of purpose

D.

Agent

Question 56

The following question requires your selection of Scenario 1.4.150 from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual depreciation (in USS) would be calculated as follows for a capital recovery with salvage analysis:

Options:

A.

5,343 par year

B.

4,343 pet year

C.

8,0X10 per year

D.

7,000 per year

Page: 1 / 19
Total 189 questions